COUPLING,TYPE NL50,A105

Material 4100011877 · COUPLING · Plant 1000

BLong-leadMaintainStockout
Material
4100011877
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
RAJAWALI TEKNIK PRATAMA PT
Lead time
103 d · P80 139 d
Unit price
Rp 31.5M

Recommendation

  • 1.Forecast 1.0 SET/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~103 days; expected demand during lead time 0.3.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 4
next delivery 15 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 31.5M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 103 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 238.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~44 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-624A
RECYCLE ETHANE BLOWER
B152.28

Lead time and procurement

Lead time 103 ± 54 days (PO history + category, 2 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
19 Jul 2026PR03
Regular replenishment
2Rp 31.4M15 Oct 2026
open
88 d
20 May 2026PR03
Regular replenishment
2Rp 31.5M03 Nov 2026
open
167 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Aug 2026MediumPX_KC-624AKC-624A high vibration
10 Aug 2026MediumPX_KC-624ALeak from packing
18 Jun 2026LowPX_KC-624AOverhaul
19 Feb 2026MediumPX_KC-624AOverhaul
25 May 2025LowPX_KC-624ARepair insulation KC-624A

Recent goods issues

Posting dateQtyOrderOrder type
20 Jun 20261201000017155Corrective