Sparely
DU

RING,WEAR,MODEL IY331,SS304

Material 4100012419 · RING · Plant 1000

AReorderNormalBelow reorder point
Material
4100012419
Category
RING
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
92 d · P80 143 d
Unit price
Rp 8.2M (est.)

Recommendation

  • 1.Forecast 1.3 EA/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~92 days; expected demand during lead time 0.3.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 24.6M · order by 01 Oct 2026
Expected arrival ≈ 92 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 8.2M
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 1 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~59 days.

Installed on 3 functional locations

3 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-103
COOLING WATER PUMP
A172.33
PX_PP-1383
PROPYLENE PUMP
A100.19
PX_PP-1484
RICH AMINE PUMP
A100.19

Lead time and procurement

Lead time 92 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026LowPX_PP-103Oil leak at PP-103 bearing housing
24 Sept 2026MediumPX_PP-103PP-103 abnormal noise
10 Jan 2026MediumPX_PP-103PP-103 seal leak
19 Nov 2025EmergencyPX_PP-103Install scaffolding at PP-103
22 Oct 2025MediumPX_PP-103[MSI-B-25-WHU-395] Permanent repair
06 Sept 2025MediumPX_PP-103PP-103 seal leak
25 May 2025MediumPX_PP-103Install scaffolding at PP-103

Recent goods issues

Posting dateQtyOrderOrder type
30 Sept 20261201000014601Corrective