GASKET,RING,1-1/2IN,300#,PTFE

Material 4100014000 · GASKET · Plant 1000

ASafety-criticalMonitorHealthy
Material
4100014000
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (188 of 307 FuncLocs A/B, 33 safety/shutdown valve)
Supplier
SAMUDRA SEJAHTERA INTERNASIONAL PT
Lead time
35 d · P80 50 d
Unit price
Rp 36,085

Recommendation

  • 1.Safety-critical element: installed on 33 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 533 EA/year: 529 unplanned (recency-weighted compound poisson (own history)) + 3.6 from the maintenance plan.
  • 3.Lead time ~35 days; expected demand during lead time 52 (incl. 1.4 planned).
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 179, order up to 650.
  • 5.Installed on 307 FuncLoc(s), 188 of them criticality A/B.
  • 6.ML early warning: 100% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 176Single sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
483 / 452
next delivery 11 Oct 2026
Today Min / Max
113 / 329
static parameters in BoM
Rec. Min (reorder point)
179
safety stock 127
Rec. Max
650
order qty 471
Service level
99.9%
stockout risk now 0%
Unit price
Rp 36,085
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 56 issue days in the last 180 days, last issue 2 days ago, 150 failure notifications on its equipment in 90 days, 3 planned jobs in 90 days, 16 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (208 units) excluded from the baseline.

Demand pattern Smooth · 175 issue days · 14 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 37.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 307 functional locations

188 with criticality A/B · 374 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-106
CRACKING FURNACE BF-106
A18230.86
PX_BF-112
CRACKING FURNACE BF-112
A17327.01
PX_BF-103
CRACKING FURNACE BF-103
A13814.58
PX_BF-109
CRACKING FURNACE BF-109
A12911.58
PX_BF-104
CRACKING FURNACE BF-104
A12811.58
PX_BF-107
CRACKING FURNACE BF-107
A1239.01
PX_KC-247A
SLOP OIL FAN
A294.00
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_HE-1334B
BOTTOM CONDENSER
A182.36
PX_PP-1776B
RICH AMINE PUMP
A183.62
PX_HE-1635C
CHARGE GAS COOLER
A171.93
PX_KC-854C
FEED FAN
A172.28

Lead time and procurement

Lead time 35 ± 25 days (PO history, 62 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
10 Sept 2026PR03
Regular replenishment
271Rp 37,26431 Oct 2026
open
51 d
31 Aug 2026PR03
Regular replenishment
314Rp 34,34026 Sept 202626 d
30 Aug 2026PR06
Regular replenishment
371Rp 36,31718 Sept 202619 d
13 Aug 2026PR03
Regular replenishment
160Rp 36,33429 Sept 202647 d
12 Aug 2026PR03
Regular replenishment
229Rp 37,21605 Sept 202624 d
05 Aug 2026PR05
Project / turnaround
259Rp 34,39402 Sept 202628 d
27 Jul 2026PR03
Regular replenishment
136Rp 36,62210 Sept 202645 d
07 Jul 2026PR03
Regular replenishment
453Rp 34,26315 Aug 202639 d
18 Jun 2026PR03
Regular replenishment
366Rp 36,15216 Jul 202628 d
05 Jun 2026PR06
Regular replenishment
372Rp 37,24518 Jun 202613 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Oct 2026PY_PP-1584BPump overhaul0.72
01 Nov 2026PX_PCV-493Final Element Overhaul; Control Valve0.72
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
19 Feb 2027PX_PCV-1400BFinal Element Overhaul; Control Valve0.72
02 Jul 2027PX_PP-135APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
30 Sept 2026MediumPX_PP-1864Install scaffolding at PP-1864
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026LowPX_BF-112Painting BF-112
28 Sept 2026LowPX_BF-106Peep door broken BF-106
28 Sept 2026MediumPX_PP-1938A[MSI-B-26-ALF-384] Permanent repair
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
26 Sept 2026LowPX_PP-1938AOverhaul PP-1938A

Recent goods issues

Posting dateQtyOrderOrder type
29 Sept 20264201000012583Corrective
27 Sept 20262201000005210Corrective
26 Sept 20262201000004515Corrective
13 Sept 20265201000035506Corrective
11 Sept 20263201000038057Corrective
07 Sept 20263201000030378Corrective
07 Sept 20263204000039956Preventive
04 Sept 20264201000014524Corrective
31 Aug 202612203000017844Turnaround
25 Aug 20263201000029784Corrective
23 Aug 20264201000000994Corrective
10 Aug 20264201000021114Corrective
03 Aug 20263201000035128Corrective
31 Jul 20262201000002390Corrective
30 Jul 20265201000038151Corrective