GASKET,SW,2IN,300#,GR/304
Material 4100014060 · GASKET · Plant 1000
ASafety-criticalReorderCriticalStockout
- Material
- 4100014060
- Category
- GASKET
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (57 of 103 FuncLocs A/B, 6 safety/shutdown valve)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 35 d · P80 40 d
- Unit price
- Rp 1.0M
Recommendation
- 1.Safety-critical element: installed on 6 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 115 EA/year: 112 unplanned (recency-weighted compound poisson (own history)) + 2.1 from the maintenance plan.
- 3.Lead time ~35 days; expected demand during lead time 11.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 42, order up to 83.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 83 now.
- 6.Installed on 103 FuncLoc(s), 57 of them criticality A/B.
- 7.ML early warning: 100% probability of demand in the next 90 days.
Proposed purchase requisition
83 EA
Rp 85.7M · order by 01 Oct 2026
Expected arrival ≈ 35 days
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 34Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
42
safety stock 32
Rec. Max
83
order qty 41
Service level
99.9%
stockout risk now 86%
Unit price
Rp 1.0M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 19 issue days in the last 180 days, last issue 1 days ago, 73 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 5 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (54 units) excluded from the baseline.
Demand pattern Smooth · 50 issue days · 4 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 11.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 103 functional locations
57 with criticality A/B · 126 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 4 | 114 | 42.86 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 1 | 71 | 28.72 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 3 | 23 | 9.01 |
| PX_KC-854C FEED FAN | A | 1 | 7 | 2.28 |
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KC-226 HYDROGEN AIR COMPRESSOR | A | 2 | 6 | 2.28 |
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 1 | 5 | 1.85 |
| PX_KC-479C DILUTION STEAM COMPRESSOR | A | 1 | 5 | 2.71 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_HE-534C SEAL OIL TLE | A | 1 | 3 | 0.65 |
| PX_CL-859 FLUSHING OIL SCRUBBER | A | 1 | 2 | 0.81 |
Lead time and procurement
Lead time 35 ± 23 days (PO history, 21 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 06 Aug 2026 | PR01 Import / long-lead | 99 | Rp 1.1M | 14 Sept 2026 | 39 d |
| 22 Jul 2026 | PR06 Regular replenishment | 79 | Rp 1.1M | 11 Aug 2026 | 20 d |
| 30 Jun 2026 | PR05 Project / turnaround | 97 | Rp 1.0M | 07 Sept 2026 | 69 d |
| 14 Jun 2026 | PR03 Regular replenishment | 44 | Rp 1.1M | 22 Jul 2026 | 38 d |
| 26 Apr 2026 | PR05 Project / turnaround | 44 | Rp 1.0M | 27 May 2026 | 31 d |
| 08 Feb 2026 | PR06 Regular replenishment | 32 | Rp 1.0M | 07 Mar 2026 | 27 d |
| 03 Dec 2025 | PR06 Regular replenishment | 83 | Rp 1.0M | 07 Jan 2026 | 35 d |
| 26 Nov 2025 | PR01 Import / long-lead | 82 | Rp 1.0M | 26 Jan 2026 | 61 d |
| 10 Nov 2025 | PR06 Regular replenishment | 78 | Rp 1.0M | 02 Dec 2025 | 22 d |
| 11 Sept 2025 | PR03 Regular replenishment | 83 | Rp 1.0M | 21 Sept 2025 | 10 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Dec 2026 | PX_PP-1952C | Pump overhaul | 0.72 |
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
| 01 Aug 2027 | PX_KC-620A | Compressor major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_PP-287D | PP-287D seal leak |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 24 Sept 2026 | Low | PX_KC-879A | Inspect coupling KC-879A |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 23 Sept 2026 | Low | PX_HE-1756B | HE-1756B tube leak |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 22 Sept 2026 | Medium | PX_KC-854C | Overhaul |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 2 | 201000020309 | Corrective |
| 30 Sept 2026 | 1 | 201000022867 | Corrective |
| 30 Sept 2026 | 1 | 201000024363 | Corrective |
| 08 Sept 2026 | 5 | 204000028728 | Preventive |
| 04 Sept 2026 | 1 | 201000009852 | Corrective |
| 28 Aug 2026 | 4 | 203000017844 | Turnaround |
| 25 Aug 2026 | 5 | 201000024850 | Corrective |
| 27 Jul 2026 | 1 | 201000009720 | Corrective |
| 23 Jul 2026 | 1 | 201000023809 | Corrective |
| 07 Jul 2026 | 5 | 204000002628 | Preventive |
| 05 Jul 2026 | 2 | 201000018095 | Corrective |
| 26 Jun 2026 | 1 | 201000001753 | Corrective |
| 24 Jun 2026 | 4 | 201000001753 | Corrective |
| 21 Jun 2026 | 6 | 209000014083 | Other maintenance |
| 17 Jun 2026 | 1 | 201000006833 | Corrective |