GASKET,SHEET,1/4IN,150#,PTFE
Material 4100014123 · GASKET · Plant 1000
ASafety-criticalReduceExcess
- Material
- 4100014123
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (18 of 28 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 24 d · P80 29 d
- Unit price
- Rp 153,588
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 62 EA/year: 62 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~24 days; expected demand during lead time 4.0.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 22, order up to 84.
- 5.Stock 150 exceeds the level to keep (84) by 66.
- 6.Installed on 28 FuncLoc(s), 18 of them criticality A/B.
- 7.ML early warning: 98% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 24Single sourceAbnormal consumption
On hand / on order
150 / 0
no open PO
Today Min / Max
72 / 161
static parameters in BoM
Rec. Min (reorder point)
22
safety stock 18
Rec. Max
84
order qty 62
Service level
100.0%
stockout risk now 0%
Unit price
Rp 153,588
PO history
ML early warning: 98% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 10 days ago, 17 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (36 units) excluded from the baseline.
Demand pattern Erratic · 27 issue days · 4 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 28 functional locations
18 with criticality A/B · 42 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-1635C CHARGE GAS COOLER | A | 1 | 7 | 1.93 |
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_CL-932 RICH AMINE COLUMN | A | 4 | 5 | 1.66 |
| PY_HE-1907A METHANE TLE | A | 2 | 3 | 1.08 |
| PX_CL-1039 CHARGE GAS STRIPPER | A | 1 | 2 | 0.81 |
| PX_KC-801 DEMIN WATER FAN | A | 1 | 2 | 1.43 |
| PX_FCV-670 GASOLINE FLOW CONTROL | A | 1 | 0 | 0.11 |
| PX_HE-1564C DILUTION STEAM TLE | A | 1 | 0 | 0.22 |
| PX_HE-895B DEMIN WATER EXCHANGER | A | 1 | 0 | 0.22 |
| PX_HE-896C GASOLINE COOLER | A | 1 | 0 | 0.22 |
| PX_PCV-576B PRESSURE CONTROL VALVE | A | 3 | 0 | 0.08 |
| PY_HE-724 ETHYLENE REBOILER | A | 1 | 0 | 0.22 |
Lead time and procurement
Lead time 24 ± 11 days (PO history, 9 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Sept 2026 | PR03 Regular replenishment | 48 | Rp 145,321 | 27 Sept 2026 | 15 d |
| 12 Aug 2026 | PR03 Regular replenishment | 57 | Rp 148,136 | 26 Aug 2026 | 14 d |
| 12 Jul 2026 | PR03 Regular replenishment | 33 | Rp 153,588 | 30 Jul 2026 | 18 d |
| 10 Jun 2026 | PR03 Regular replenishment | 46 | Rp 154,550 | 19 Jun 2026 | 9 d |
| 05 Mar 2026 | PR06 Regular replenishment | 22 | Rp 152,013 | 26 Mar 2026 | 21 d |
| 29 Dec 2025 | PR03 Regular replenishment | 65 | Rp 153,623 | 23 Jan 2026 | 25 d |
| 18 Oct 2025 | PR03 Regular replenishment | 49 | Rp 154,591 | 21 Nov 2025 | 34 d |
| 24 Jun 2025 | PR03 Regular replenishment | 44 | Rp 151,471 | 11 Jul 2025 | 17 d |
| 09 Jun 2025 | PR06 Regular replenishment | 29 | Rp 153,945 | 18 Jul 2025 | 39 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_KC-879A | Inspect coupling KC-879A |
| 23 Sept 2026 | Medium | PX_KC-513 | KC-513 high vibration |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 07 Sept 2026 | Medium | PX_KC-513 | Inspect coupling KC-513 |
| 07 Sept 2026 | Medium | PX_KC-879A | Replace lamp as per PM finding |
| 05 Sept 2026 | Low | PX_KC-513 | Inspect coupling KC-513 |
| 03 Sept 2026 | Medium | PX_CL-443 | Replace lamp as per PM finding |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 31 Aug 2026 | Low | PX_CL-932 | CL-932 DP high |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Sept 2026 | 3 | 201000006305 | Corrective |
| 04 Sept 2026 | 3 | 201000030139 | Corrective |
| 25 Aug 2026 | 1 | 201000037723 | Corrective |
| 24 Aug 2026 | 3 | 201000022703 | Corrective |
| 23 Aug 2026 | 1 | 201000023643 | Corrective |
| 23 Jun 2026 | 2 | 201000013317 | Corrective |
| 17 May 2026 | 4 | 201000009393 | Corrective |
| 26 Apr 2026 | 2 | 201000000645 | Corrective |
| 10 Feb 2026 | 4 | 203000018609 | Turnaround |
| 27 Jan 2026 | 10 | 203000033471 | Turnaround |
| 05 Jan 2026 | 2 | 201000025317 | Corrective |
| 04 Jan 2026 | 1 | 201000023806 | Corrective |
| 25 Dec 2025 | 14 | 203000016277 | Turnaround |
| 11 Dec 2025 | 3 | 201000037273 | Corrective |
| 07 Dec 2025 | 3 | 201000037867 | Corrective |