GASKET,SHEET,1-1/2IN,600#,GRAPHITE
Material 4100014165 · GASKET · Plant 1000
ASafety-criticalMonitorHealthy
- Material
- 4100014165
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (21 of 39 FuncLocs A/B, 7 safety/shutdown valve)
- Supplier
- PRIMA LOGAM NUSANTARA PT
- Lead time
- 46 d · P80 62 d
- Unit price
- Rp 49,031
Recommendation
- 1.Safety-critical element: installed on 7 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 43 EA/year: 42 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
- 3.Lead time ~46 days; expected demand during lead time 5.2.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 21, order up to 64.
- 5.Installed on 39 FuncLoc(s), 21 of them criticality A/B.
- 6.ML early warning: 96% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 8Single sourceAbnormal consumptionOpen PO
On hand / on order
48 / 30
next delivery 14 Nov 2026
Today Min / Max
33 / 101
static parameters in BoM
Rec. Min (reorder point)
21
safety stock 16
Rec. Max
64
order qty 43
Service level
100.0%
stockout risk now 0%
Unit price
Rp 49,031
PO history
ML early warning: 96% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 5 days ago, 26 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (34 units) excluded from the baseline.
Demand pattern Intermittent · 17 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 39 functional locations
21 with criticality A/B · 49 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-102 CRACKING FURNACE BF-102 | A | 1 | 71 | 28.72 |
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_SDV-1011A HE-1229B SHUTDOWN VALVE | A | 1 | 4 | 1.34 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_FCV-1732 BFW FLOW CONTROL | A | 1 | 1 | 0.11 |
| PX_HE-347A QUENCH OIL PREHEATER | A | 1 | 1 | 0.22 |
| PX_PP-1801A DEMIN WATER PUMP | A | 1 | 1 | 0.19 |
| PX_FCV-1467A CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_HE-1481 CAUSTIC COOLER | A | 1 | 0 | 0.22 |
| PX_HE-1797C FUEL OIL PREHEATER | A | 3 | 0 | 0.22 |
| PX_HE-826D GASOLINE CONDENSER | A | 1 | 0 | 0.22 |
Lead time and procurement
Lead time 46 ± 31 days (PO history, 6 PO lines) · on-time 34%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Jul 2026 | PR05 Project / turnaround | 30 | Rp 49,549 | 14 Nov 2026 open | 126 d |
| 24 Jun 2026 | PR05 Project / turnaround | 11 | Rp 49,279 | 25 Aug 2026 | 62 d |
| 16 Jun 2026 | PR03 Regular replenishment | 34 | Rp 50,720 | 20 Jul 2026 | 34 d |
| 04 Nov 2025 | PR03 Regular replenishment | 22 | Rp 48,338 | 21 Dec 2025 | 47 d |
| 17 Oct 2025 | PR04 Regular (other) | 37 | Rp 48,436 | 15 Nov 2025 | 29 d |
| 13 Jun 2025 | PR03 Regular replenishment | 27 | Rp 48,782 | 02 Jul 2025 | 19 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Feb 2027 | PX_FCV-1732 | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 19 Sept 2026 | Medium | PX_HE-272 | Install cover plate for MCP cracking |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Low | PX_HE-471C | HE-471C fouling |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 07 Sept 2026 | Low | PX_BF-102 | Thermograph wall BF-102 |
| 06 Sept 2026 | Medium | PX_BF-102 | Decoking follow up BF-102 |
| 03 Sept 2026 | Medium | PX_BF-102 | Replace lamp as per PM finding |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Sept 2026 | 2 | 201000025207 | Corrective |
| 10 Aug 2026 | 3 | 201000002413 | Corrective |
| 07 Aug 2026 | 1 | 201000005043 | Corrective |
| 02 Aug 2026 | 1 | 201000026506 | Corrective |
| 25 May 2026 | 1 | 201000012062 | Corrective |
| 24 Apr 2026 | 4 | 203000034130 | Turnaround |
| 18 Apr 2026 | 8 | 201000006270 | Corrective |
| 03 Mar 2026 | 2 | 201000014462 | Corrective |
| 09 Feb 2026 | 1 | 201000021442 | Corrective |
| 30 Jan 2026 | 2 | 201000038591 | Corrective |
| 28 Jan 2026 | 4 | 201000035426 | Corrective |
| 20 Jan 2026 | 1 | 201000039436 | Corrective |
| 24 Dec 2025 | 5 | 201000002755 | Corrective |
| 12 Dec 2025 | 4 | 201000001111 | Corrective |
| 06 Dec 2025 | 6 | 203000014228 | Turnaround |