GASKET,RING,1IN,300#,PTFE

Material 4100014252 · GASKET · Plant 1000

ASafety-criticalReduceExcess
Material
4100014252
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (17 of 27 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
CAHAYA INDUSTRI SENTOSA PT
Lead time
32 d · P80 39 d
Unit price
Rp 126,802

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 23 EA/year: 23 unplanned (recency-weighted compound poisson (own history)).
  • 3.Lead time ~32 days; expected demand during lead time 2.0.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 35.
  • 5.Stock 41 exceeds the level to keep (35) by 6.
  • 6.Installed on 27 FuncLoc(s), 17 of them criticality A/B.
  • 7.ML early warning: 88% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 32Single source
On hand / on order
41 / 0
no open PO
Today Min / Max
9 / 18
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 10
Rec. Max
35
order qty 23
Service level
100.0%
stockout risk now 0%
Unit price
Rp 126,802
PO history
ML early warning: 88% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 48 days ago, 30 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (32 units) excluded from the baseline.

Demand pattern Lumpy · 11 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 27 functional locations

17 with criticality A/B · 31 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-103
CRACKING FURNACE BF-103
A13814.58
PX_HE-1483A
C4 PRODUCT COOLER
A1113.22
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-222B
LEAN AMINE COMPRESSOR
A151.85
PX_KC-316D
METHANOL FAN
A151.43
PX_PP-1022
QUENCH WATER PUMP
A131.47
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_PCV-1709B
BY PASS DUCT
A110.08
PX_HE-606D
DEMIN WATER COOLER
A100.22
PX_MOV-1524
MOTOR OPERATED GATE VALVE
A100.06
PX_PP-641A
GASOLINE PUMP
A100.19
PX_HE-786
ETHYLENE COOLER
B141.08

Lead time and procurement

Lead time 32 ± 12 days (PO history, 12 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
02 Aug 2026PR03
Regular replenishment
28Rp 122,60025 Aug 202623 d
20 Apr 2026PR03
Regular replenishment
17Rp 128,39519 May 202629 d
02 Mar 2026PR06
Regular replenishment
23Rp 129,53926 Mar 202624 d
29 Jan 2026PR03
Regular replenishment
9Rp 123,53315 Feb 202617 d
27 Jan 2026PR05
Project / turnaround
21Rp 130,45927 Mar 202659 d
11 Jan 2026PR03
Regular replenishment
16Rp 121,21517 Feb 202637 d
22 Oct 2025PR03
Regular replenishment
28Rp 121,75301 Dec 202540 d
20 Sept 2025PR03
Regular replenishment
28Rp 125,20819 Oct 202529 d
30 Aug 2025PR03
Regular replenishment
23Rp 119,58109 Oct 202540 d
29 Aug 2025PR03
Regular replenishment
12Rp 129,60004 Oct 202536 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
23 Sept 2026MediumPX_HE-1483AHE-1483A fouling
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
16 Sept 2026MediumPX_HE-786Leak from packing
15 Sept 2026MediumPX_BF-103Replace lamp as per PM finding
15 Sept 2026MediumPX_BF-110Decoking follow up BF-110
11 Sept 2026MediumPX_BF-103Decoking follow up BF-103

Recent goods issues

Posting dateQtyOrderOrder type
14 Aug 20261201000011746Corrective
15 Jul 20261201000026330Corrective
10 May 20262204000019410Preventive
25 Feb 20265204000028926Preventive
20 Jan 20261201000015985Corrective
28 Dec 202514203000006078Turnaround
20 Dec 20252201000033420Corrective
18 Dec 20251201000008954Corrective
05 Dec 20255201000018271Corrective
28 Nov 20254203000009623Turnaround
07 Nov 20252203000033996Turnaround
01 Nov 202512203000039255Turnaround
28 Aug 20252209000035104Other maintenance
29 May 20251201000027735Corrective
19 May 20255201000014175Corrective