GASKET,RING,1/4IN,300#,GRAPHITE
Material 4100014289 · GASKET · Plant 1000
AMonitorHealthy
- Material
- 4100014289
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (17 of 23 FuncLocs A/B)
- Supplier
- SINAR TEKNIK INTERNASIONAL PT
- Lead time
- 31 d · P80 38 d
- Unit price
- Rp 211,811
Recommendation
- 1.Forecast 17 EA/year: 17 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~31 days; expected demand during lead time 1.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 27.
- 4.Installed on 23 FuncLoc(s), 17 of them criticality A/B.
- 5.ML early warning: 89% probability of demand in the next 90 days.
ML early warningLast turnaround used 10Single sourceAbnormal consumptionOpen PO
On hand / on order
4 / 7
next delivery 19 Oct 2026
Today Min / Max
3 / 8
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 9
Rec. Max
27
order qty 17
Service level
100.0%
stockout risk now 0%
Unit price
Rp 211,811
PO history
ML early warning: 89% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 99 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (10 units) excluded from the baseline.
Demand pattern Lumpy · 11 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 23 functional locations
17 with criticality A/B · 29 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_CL-859 FLUSHING OIL SCRUBBER | A | 1 | 2 | 0.81 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_HE-921C FUEL OIL EXCHANGER | A | 1 | 1 | 0.22 |
| PX_PP-592 FLUSHING OIL PUMP | A | 1 | 1 | 0.19 |
| PY_KC-636C SLOP OIL COMPRESSOR | A | 1 | 1 | 0.57 |
| PX_CL-797 C4 PRODUCT TOWER | A | 1 | 0 | 0.38 |
| PX_HE-826D GASOLINE CONDENSER | A | 1 | 0 | 0.22 |
| PX_KC-886D BOTTOM FAN | B | 4 | 4 | 1.43 |
| PX_PP-1928 FUEL OIL PUMP | B | 2 | 3 | 1.05 |
| PX_LCV-114 LEVEL CONTROL VALVE | B | 1 | 1 | 0.12 |
| PX_FCV-1761 FLUSHING OIL FLOW CONTROL | B | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 31 ± 16 days (PO history, 9 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 Aug 2026 | PR03 Regular replenishment | 7 | Rp 212,142 | 19 Oct 2026 open | 64 d |
| 24 Jul 2026 | PR03 Regular replenishment | 14 | Rp 211,811 | 24 Aug 2026 | 31 d |
| 24 Jun 2026 | PR04 Regular (other) | 13 | Rp 203,645 | 27 Jul 2026 | 33 d |
| 04 Jan 2026 | PR06 Regular replenishment | 9 | Rp 209,746 | 16 Jan 2026 | 12 d |
| 31 Oct 2025 | PR03 Regular replenishment | 13 | Rp 213,676 | 22 Nov 2025 | 22 d |
| 15 Oct 2025 | PR05 Project / turnaround | 13 | Rp 204,755 | 29 Nov 2025 | 45 d |
| 27 Sept 2025 | PR03 Regular replenishment | 13 | Rp 211,003 | 22 Oct 2025 | 25 d |
| 15 Jul 2025 | PR03 Regular replenishment | 16 | Rp 212,121 | 17 Aug 2025 | 33 d |
| 11 May 2025 | PR06 Regular replenishment | 15 | Rp 215,426 | 28 May 2025 | 17 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Low | PX_KC-886D | KC-886D high vibration |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 16 Aug 2026 | Medium | PX_BF-101 | Install scaffolding at BF-101 |
| 10 Jul 2026 | Medium | PX_KC-886D | Install scaffolding at KC-886D |
| 08 Jul 2026 | High | PX_PP-1928 | PP-1928 discharge pressure low |
| 08 Jul 2026 | Medium | PX_PP-298C | Replace lamp as per PM finding |
| 27 Jun 2026 | Low | PX_PP-298C | Oil leak at PP-298C bearing housing |
| 22 Jun 2026 | Low | PX_BF-101 | Thermograph wall BF-101 |
| 06 Jun 2026 | Emergency | PX_BF-101 | Decoking follow up BF-101 |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Jun 2026 | 3 | 201000034485 | Corrective |
| 02 Apr 2026 | 1 | 201000026925 | Corrective |
| 03 Mar 2026 | 2 | 205000027982 | Other maintenance |
| 12 Feb 2026 | 5 | 201000015484 | Corrective |
| 27 Jan 2026 | 2 | 201000030347 | Corrective |
| 25 Dec 2025 | 1 | 201000021137 | Corrective |
| 22 Dec 2025 | 2 | 203000022966 | Turnaround |
| 17 Dec 2025 | 2 | 201000027804 | Corrective |
| 22 Nov 2025 | 9 | 201000004704 | Corrective |
| 06 Nov 2025 | 6 | 203000039255 | Turnaround |
| 03 Nov 2025 | 1 | 201000038265 | Corrective |
| 03 Nov 2025 | 2 | 203000039255 | Turnaround |
| 17 Oct 2025 | 1 | 201000004804 | Corrective |
| 13 Sept 2025 | 2 | 209000031163 | Other maintenance |