GASKET,RING,4IN,300#,GR/304

Material 4100014324 · GASKET · Plant 1000

ASafety-criticalMonitorStockout
Material
4100014324
Category
GASKET
Base unit
EA
MRP type
Non Stock
Criticality
A (13 of 18 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
RAJAWALI INSTRUMEN INTERNASIONAL PT
Lead time
39 d · P80 50 d
Unit price
Rp 1.6M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 32 EA/year: 31 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 3.Lead time ~39 days; expected demand during lead time 3.2.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 17, order up to 35.
  • 5.Installed on 18 FuncLoc(s), 13 of them criticality A/B.
  • 6.ML early warning: 86% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 2Single sourceOpen PO
On hand / on order
0 / 21
next delivery 08 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
17
safety stock 14
Rec. Max
35
order qty 18
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.6M
PO history
ML early warning: 86% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 7 days ago, 14 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (2 units) excluded from the baseline.

Demand pattern Intermittent · 12 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 18 functional locations

13 with criticality A/B · 21 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-109
CRACKING FURNACE BF-109
A12911.58
PX_CL-457
FEED SCRUBBER
A1113.80
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_FCV-1644
VD-981A OUTLET FLOW
A120.11
PX_KC-588
CAUSTIC FAN
A121.00
PX_PRV-929A
SAFETY VALVE PP-1076A
A110.04
PX_KC-618B
WASH WATER BLOWER
A100.57
PX_LCV-150
HE-492C LEVEL CONTROL
A100.12
PX_PCV-1400B
PRESSURE CONTROL VALVE
A100.08
UT_VD-1010A
REFLUX KO DRUM
A100.08
PX_KC-620A
DEMIN WATER AIR COMPRESSOR
B121.00
PX_BF-101-QF17
DILUTION STEAM TO MIXED FEED COIL
B100.45

Lead time and procurement

Lead time 39 ± 28 days (PO history, 9 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
18 Sept 2026PR06
Regular replenishment
12Rp 1.6M08 Oct 2026
open
20 d
21 Jul 2026PR04
Regular (other)
9Rp 1.6M16 Nov 2026
open
118 d
02 Jul 2026PR03
Regular replenishment
9Rp 1.6M07 Aug 202636 d
22 Jun 2026PR06
Regular replenishment
14Rp 1.7M06 Jul 202614 d
30 May 2026PR06
Regular replenishment
21Rp 1.6M26 Jun 202627 d
19 Dec 2025PR06
Regular replenishment
11Rp 1.6M18 Jan 202630 d
21 Nov 2025PR06
Regular replenishment
7Rp 1.7M24 Jan 202664 d
20 Nov 2025PR05
Project / turnaround
7Rp 1.7M12 Dec 202522 d
09 Oct 2025PR04
Regular (other)
16Rp 1.6M18 Nov 202540 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
19 Feb 2027PX_PCV-1400BFinal Element Overhaul; Control Valve0.72
01 Aug 2027PX_KC-620ACompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Sept 2026MediumPX_BF-109Thermograph wall BF-109
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
15 Sept 2026MediumPX_CL-457CL-457 DP high
13 Sept 2026MediumPX_BF-109Install scaffolding at BF-109
03 Sept 2026LowPX_BF-109Install scaffolding at BF-109
02 Sept 2026LowPX_BF-109Install cover plate for MCP cracking
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
21 Aug 2026MediumPX_CL-457Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
24 Sept 20261201000009714Corrective
22 Sept 20263201000009714Corrective
06 Sept 20261201000004876Corrective
15 Jul 20261201000025691Corrective
23 Dec 20252203000033370Turnaround
17 Dec 20252209000020420Other maintenance
20 Nov 20253201000030034Corrective
16 Nov 20251201000017157Corrective
29 Sept 20258201000025755Corrective
16 Aug 20254201000027093Corrective
09 Aug 20251201000014472Corrective
03 Aug 20253204000037748Preventive
05 Jul 20256209000007603Other maintenance
04 Jun 20258201000025970Corrective