GASKET,SW,1/4IN,150#,GR/304
Material 4100014450 · GASKET · Plant 1000
ASafety-criticalReorderNormalBelow reorder point
- Material
- 4100014450
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (9 of 13 FuncLocs A/B, 3 safety/shutdown valve)
- Supplier
- BUANA TEKNIK SENTOSA PT
- Lead time
- 29 d · P80 29 d
- Unit price
- Rp 847,950
Recommendation
- 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 23 EA/year: 23 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~29 days; expected demand during lead time 1.9.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 17, order up to 38.
- 5.On hand 11 + on order 0 is at or below the reorder point: order 27 now.
- 6.Installed on 13 FuncLoc(s), 9 of them criticality A/B.
- 7.ML early warning: 42% probability of demand in the next 90 days.
Proposed purchase requisition
27 EA
Rp 22.9M · order by 01 Oct 2026
Expected arrival ≈ 29 days
Safety-critical (SCE)ML early warningLast turnaround used 10Single source
On hand / on order
11 / 0
no open PO
Today Min / Max
6 / 11
static parameters in BoM
Rec. Min (reorder point)
17
safety stock 16
Rec. Max
38
order qty 21
Service level
100.0%
stockout risk now 4%
Unit price
Rp 847,950
PO history
ML early warning: 42% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 1 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (10 units) excluded from the baseline.
Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 13 functional locations
9 with criticality A/B · 16 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PX_FCV-1295 CL-1039 OUTLET FLOW | A | 1 | 0 | 0.11 |
| PX_KC-618B WASH WATER BLOWER | A | 1 | 0 | 0.57 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_PP-1821 CAUSTIC PUMP | A | 1 | 0 | 0.19 |
| PX_PRV-1448A SAFETY VALVE VD-664B | A | 1 | 0 | 0.04 |
| PX_PP-1577D ETHYLENE PUMP | B | 2 | 2 | 1.05 |
| PX_HE-1529C ETHYLENE COOLER | B | 1 | 1 | 0.22 |
| PX_PRV-1800 SAFETY VALVE HE-786 | B | 1 | 0 | 0.04 |
| PX_6-FG-29895-A51A PIPE-6 FROM KC-854C TO VD-531 | C | 1 | 0 | 0.01 |
| PX_PP-1141D DILUTION STEAM PUMP | C | 1 | 0 | 0.19 |
| PX_FCV-1912 HE-1363A OUTLET FLOW | S | 3 | 3 | 1.39 |
Lead time and procurement
Lead time 29 ± 10 days (PO history, 3 PO lines) · on-time 29%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 20 Jun 2026 | PR04 Regular (other) | 15 | Rp 819,890 | 14 Jul 2026 | 24 d |
| 12 Apr 2026 | PR03 Regular replenishment | 6 | Rp 847,950 | 09 May 2026 | 27 d |
| 24 Mar 2026 | PR03 Regular replenishment | 11 | Rp 868,857 | 24 Apr 2026 | 31 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 07 Sept 2026 | Medium | PX_PP-1577D | Replace bearing PP-1577D |
| 15 Aug 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 08 Aug 2026 | Low | PX_BF-107 | Cleaning burner BF-107 |
| 21 Jul 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 21 Jul 2026 | Medium | PX_BF-107 | Thermograph wall BF-107 |
| 18 Jul 2026 | Emergency | PX_BF-107 | Hot spot at convection BF-107 |
| 10 Jul 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 12 Apr 2026 | Medium | PX_BF-107 | Decoking follow up BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 2 | 201000006629 | Corrective |
| 29 Dec 2025 | 6 | 203000006078 | Turnaround |
| 26 Dec 2025 | 4 | 201000011308 | Corrective |
| 26 Dec 2025 | 1 | 201000026349 | Corrective |
| 05 Dec 2025 | 4 | 203000037280 | Turnaround |
| 27 Nov 2025 | 10 | 201000004062 | Corrective |
| 14 Sept 2025 | 7 | 201000019175 | Corrective |
| 15 Aug 2025 | 4 | 201000019582 | Corrective |