GASKET,RING,8IN,300#,GR/304
Material 4100014597 · GASKET · Plant 1000
ASafety-criticalMonitorSlow-moving
- Material
- 4100014597
- Category
- GASKET
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (6 of 12 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- GEMILANG LOGAM MAKMUR PT
- Lead time
- 38 d · P80 61 d
- Unit price
- Rp 855,090
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 5.5 EA/year: 5.5 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~38 days; expected demand during lead time 0.6.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 12.
- 5.Installed on 12 FuncLoc(s), 6 of them criticality A/B.
- 6.ML early warning: 71% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 28Single sourceOpen PO
On hand / on order
6 / 21
next delivery 03 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
12
order qty 6
Service level
100.0%
stockout risk now 0%
Unit price
Rp 855,090
PO history
ML early warning: 71% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 199 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (28 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 881.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 12 functional locations
6 with criticality A/B · 12 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-888A CONDENSATE PUMP | A | 1 | 6 | 1.90 |
| PX_HE-1097A ETHYLENE CONDENSER | A | 1 | 0 | 0.22 |
| PY_CL-454 C3 RECYCLE TOWER | A | 1 | 0 | 0.38 |
| PX_HE-344D BFW PREHEATER | B | 1 | 1 | 0.65 |
| PX_HE-1919A QUENCH WATER CONDENSER | B | 1 | 0 | 0.22 |
| PX_PP-1205A DEMIN WATER PUMP | B | 1 | 0 | 0.19 |
| PX_HE-1912 QUENCH OIL EXCHANGER | C | 1 | 4 | 1.08 |
| PX_1-IA-7369-B23A PIPE-1 FROM PP-315A TO HE-1647D | C | 1 | 1 | 0.44 |
| PX_LCV-1953 HE-1441D LEVEL CONTROL | C | 1 | 1 | 0.12 |
| PX_KC-458D SLOP OIL FAN | S | 1 | 9 | 3.14 |
| PX_SDV-200A CL-1578 SHUTDOWN VALVE | S | 1 | 2 | 0.48 |
| PX_KC-373B CONDENSATE BLOWER | S | 1 | 0 | 0.57 |
Lead time and procurement
Lead time 38 ± 19 days (PO history, 5 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 04 Sept 2026 | PR06 Regular replenishment | 21 | Rp 856,726 | 03 Oct 2026 open | 29 d |
| 02 Aug 2026 | PR06 Regular replenishment | 15 | Rp 818,339 | 15 Aug 2026 | 13 d |
| 11 May 2026 | PR06 Regular replenishment | 18 | Rp 855,015 | 22 Jun 2026 | 42 d |
| 13 Nov 2025 | PR05 Project / turnaround | 11 | Rp 869,964 | 12 Jan 2026 | 60 d |
| 11 Sept 2025 | PR06 Regular replenishment | 20 | Rp 855,090 | 14 Nov 2025 | 64 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | Medium | PX_PP-888A | Oil leak at PP-888A bearing housing |
| 19 Sept 2026 | Medium | PX_KC-458D | KC-458D lube oil filter DP high |
| 16 Sept 2026 | Low | PX_KC-458D | KC-458D lube oil filter DP high |
| 16 Aug 2026 | High | PX_PP-888A | PP-888A abnormal noise |
| 02 Aug 2026 | Medium | PX_HE-1912 | Replace lamp as per PM finding |
| 24 Jun 2026 | Medium | PX_KC-458D | KC-458D bearing temp high |
| 26 May 2026 | Medium | PX_PP-888A | PP-888A abnormal noise |
| 25 Apr 2026 | Low | PX_PP-888A | Install scaffolding at PP-888A |
| 15 Mar 2026 | Medium | PX_KC-458D | Painting KC-458D |
| 13 Mar 2026 | Medium | PX_HE-1912 | Install scaffolding at HE-1912 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 16 Mar 2026 | 1 | 201000018051 | Corrective |
| 06 Jan 2026 | 2 | 201000017484 | Corrective |
| 29 Dec 2025 | 16 | 203000033731 | Turnaround |
| 03 Dec 2025 | 12 | 203000014228 | Turnaround |
| 28 Oct 2025 | 3 | 201000032155 | Corrective |
| 04 Aug 2025 | 2 | 201000027512 | Corrective |