GASKET,SHEET,1-1/2IN,150#,GRAPHITE

Material 4100014612 · GASKET · Plant 1000

AReorderNormalBelow reorder point
Material
4100014612
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 7 FuncLocs A/B)
Supplier
RAJAWALI INSTRUMEN INTERNASIONAL PT
Lead time
30 d · P80 34 d
Unit price
Rp 314,586

Recommendation

  • 1.Forecast 4.6 EA/year: 4.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~30 days; expected demand during lead time 0.4.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 9.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 7 now.
  • 5.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
7 EA
Rp 2.2M · order by 01 Oct 2026
Expected arrival ≈ 30 days
Single source
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
9
order qty 5
Service level
100.0%
stockout risk now 3%
Unit price
Rp 314,586
PO history
ML early warning: 29% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 3 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 7 functional locations

4 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1909A
QUENCH WATER PUMP
A110.19
PX_HE-1256A
REFLUX PREHEATER
A100.22
PX_FCV-545
BY PASS LINE
B120.54
PX_HE-1287D
CHARGE GAS CONDENSER
B110.22
PX_LCV-637
LEVEL CONTROL VALVE
C100.12
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KT-875
TURBINE FOR KC-875
S101.10

Lead time and procurement

Lead time 30 ± 13 days (PO history, 3 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
10 Feb 2026PR06
Regular replenishment
1Rp 317,34509 Mar 202627 d
24 Aug 2025PR03
Regular replenishment
1Rp 306,68315 Sept 202522 d
16 Aug 2025PR03
Regular replenishment
1Rp 314,58624 Sept 202539 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
14 Mar 2026MediumPX_KT-447KT-447 steam leak at gland
14 Jan 2026MediumPX_KT-447Follow up after steam upset KT-447
21 Nov 2025MediumPX_KT-447Leak from packing
19 Nov 2025MediumPX_KT-447Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
28 Sept 20261201000001477Corrective
03 Aug 20261201000002940Corrective
08 Oct 20252201000031221Corrective