Sparely
DU

GASKET,RING,10IN,300#,PTFE

Material 4100014660 · GASKET · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100014660
Category
GASKET
Base unit
EA
MRP type
Non Stock
Criticality
A (6 of 11 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
No PO history
Lead time
31 d · P80 51 d
Unit price
Rp 214,454 (est.)

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 39 EA/year: 39 unplanned (recency-weighted compound poisson (own history)).
  • 3.Lead time ~31 days; expected demand during lead time 3.3.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 21, order up to 61.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 61 now.
  • 6.Installed on 11 FuncLoc(s), 6 of them criticality A/B.
  • 7.ML early warning: 62% probability of demand in the next 90 days.
Proposed purchase requisition
61 EA
Rp 13.1M · order by 01 Oct 2026
Expected arrival ≈ 31 days
Safety-critical (SCE)ML early warningConvert to Stock ItemPrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
21
safety stock 18
Rec. Max
61
order qty 40
Service level
99.9%
stockout risk now 47%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 62% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 4 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Lumpy · 8 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 11 functional locations

6 with criticality A/B · 18 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-713B
SPENT CAUSTIC FAN
A163.14
PX_KC-396
WASH WATER BLOWER
A331.43
PX_KC-663A
CONDENSATE FAN
A110.57
PX_CL-797
C4 PRODUCT TOWER
A400.38
PX_HE-1026
METHANE TLE
A100.22
PX_HE-578D
SEAL OIL TLE
B131.08
PX_1-1/2-HS-16028-B23A-C
PIPE-1-1/2 FROM HE-1788D TO HE-1217C
C110.01
PX_3/4-IA-21403-B23A-T
PIPE-3/4 FROM HE-1966D TO VD-973
C100.01
PX_PRV-828A
SAFETY VALVE PP-684A
S310.04
PX_PRV-1365
SAFETY VALVE VD-890A
S100.04
UT_PRV-250B
SAFETY VALVE PP-745
S100.04

Lead time and procurement

Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
20 Sept 2026MediumPX_HE-578DInstall scaffolding at HE-578D
17 Jun 2026LowPX_KC-713BLeak from packing
12 Jun 2026HighPX_KC-713BInspect coupling KC-713B
17 May 2026LowPX_KC-396Overhaul
14 Apr 2026MediumPX_HE-578DReplace lamp as per PM finding
08 Apr 2026MediumPX_KC-713BInspect coupling KC-713B
13 Oct 2025EmergencyPX_KC-713BLeak from packing
29 Aug 2025LowPX_KC-713BLeak from packing
14 Aug 2025MediumPX_HE-578DHE-578D fouling

Recent goods issues

Posting dateQtyOrderOrder type
27 Sept 202611201000010887Corrective
15 Sept 20263201000014368Corrective
14 Sept 20262209000036917Other maintenance
03 Jul 202610209000017779Other maintenance
06 Jun 20262201000003690Corrective
24 Mar 20261201000010975Corrective
12 Jan 20264201000014699Corrective
29 Aug 20259204000013152Preventive