GASKET,SHEET,12IN,300#,GRAPHITE
Material 4100014744 · GASKET · Plant 1000
AReorderCriticalStockout
- Material
- 4100014744
- Category
- GASKET
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- KARYA UTAMA GLOBAL PT
- Lead time
- 28 d · P80 34 d
- Unit price
- Rp 131,512
Recommendation
- 1.Forecast 8.9 EA/year: 8.9 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~28 days; expected demand during lead time 0.7.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 16.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 16 now.
- 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
- 6.ML early warning: 32% probability of demand in the next 90 days.
Proposed purchase requisition
16 EA
Rp 2.1M · order by 01 Oct 2026
Expected arrival ≈ 28 days
ML early warningConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 7
Rec. Max
16
order qty 9
Service level
100.0%
stockout risk now 27%
Unit price
Rp 131,512
PO history
ML early warning: 32% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 8 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 4 functional locations
2 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-247A SLOP OIL FAN | A | 1 | 9 | 4.00 |
| PX_VD-1953 QUENCH OIL KO DRUM | B | 1 | 1 | 0.08 |
| PX_CL-244 QUENCH WATER TOWER | S | 3 | 1 | 0.81 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 28 ± 18 days (PO history, 4 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 07 Sept 2026 | PR03 Regular replenishment | 5 | Rp 129,504 | 19 Sept 2026 | 12 d |
| 01 Apr 2026 | PR06 Regular replenishment | 4 | Rp 134,306 | 21 Apr 2026 | 20 d |
| 27 Jan 2026 | PR06 Regular replenishment | 2 | Rp 128,547 | 13 Feb 2026 | 17 d |
| 28 Sept 2025 | PR01 Import / long-lead | 5 | Rp 133,519 | 21 Nov 2025 | 54 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 Aug 2026 | High | PX_KC-247A | Inspect coupling KC-247A |
| 14 Jul 2026 | Medium | PX_KC-247A | Replace lamp as per PM finding |
| 29 Jun 2026 | Low | PX_KC-247A | KC-247A high vibration |
| 04 Jun 2026 | Low | PX_KC-247A | KC-247A bearing temp high |
| 06 Apr 2026 | Medium | PX_KC-247A | KC-247A bearing temp high |
| 20 Nov 2025 | Medium | PX_KC-247A | Replace lamp as per PM finding |
| 22 Aug 2025 | Low | PX_KC-247A | Overhaul |
| 09 Aug 2025 | High | PX_KC-247A | Inspect coupling KC-247A |
| 16 Jun 2025 | Medium | PX_CL-244 | Leak from packing |
| 26 May 2025 | High | PX_VD-1953 | [MSI-B-25-JAV-174/M] Replace line |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 23 Sept 2026 | 4 | 209000029477 | Other maintenance |
| 11 May 2026 | 1 | 201000011420 | Corrective |
| 14 Feb 2026 | 3 | 201000013371 | Corrective |
| 06 Jan 2026 | 1 | 201000009767 | Corrective |
| 26 Oct 2025 | 1 | 201000020408 | Corrective |
| 14 Sept 2025 | 3 | 201000034464 | Corrective |