GASKET,SHEET,12IN,300#,GRAPHITE

Material 4100014744 · GASKET · Plant 1000

AReorderCriticalStockout
Material
4100014744
Category
GASKET
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 4 FuncLocs A/B)
Supplier
KARYA UTAMA GLOBAL PT
Lead time
28 d · P80 34 d
Unit price
Rp 131,512

Recommendation

  • 1.Forecast 8.9 EA/year: 8.9 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~28 days; expected demand during lead time 0.7.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 16.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 16 now.
  • 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
  • 6.ML early warning: 32% probability of demand in the next 90 days.
Proposed purchase requisition
16 EA
Rp 2.1M · order by 01 Oct 2026
Expected arrival ≈ 28 days
ML early warningConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 7
Rec. Max
16
order qty 9
Service level
100.0%
stockout risk now 27%
Unit price
Rp 131,512
PO history
ML early warning: 32% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 8 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 4 functional locations

2 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-247A
SLOP OIL FAN
A194.00
PX_VD-1953
QUENCH OIL KO DRUM
B110.08
PX_CL-244
QUENCH WATER TOWER
S310.81
PX_KT-778A
TURBINE FOR KC-778A
S101.10

Lead time and procurement

Lead time 28 ± 18 days (PO history, 4 PO lines) · on-time 45%

PR dateTypeQtyUnit priceDeliveryLead time
07 Sept 2026PR03
Regular replenishment
5Rp 129,50419 Sept 202612 d
01 Apr 2026PR06
Regular replenishment
4Rp 134,30621 Apr 202620 d
27 Jan 2026PR06
Regular replenishment
2Rp 128,54713 Feb 202617 d
28 Sept 2025PR01
Import / long-lead
5Rp 133,51921 Nov 202554 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 Aug 2026HighPX_KC-247AInspect coupling KC-247A
14 Jul 2026MediumPX_KC-247AReplace lamp as per PM finding
29 Jun 2026LowPX_KC-247AKC-247A high vibration
04 Jun 2026LowPX_KC-247AKC-247A bearing temp high
06 Apr 2026MediumPX_KC-247AKC-247A bearing temp high
20 Nov 2025MediumPX_KC-247AReplace lamp as per PM finding
22 Aug 2025LowPX_KC-247AOverhaul
09 Aug 2025HighPX_KC-247AInspect coupling KC-247A
16 Jun 2025MediumPX_CL-244Leak from packing
26 May 2025HighPX_VD-1953[MSI-B-25-JAV-174/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
23 Sept 20264209000029477Other maintenance
11 May 20261201000011420Corrective
14 Feb 20263201000013371Corrective
06 Jan 20261201000009767Corrective
26 Oct 20251201000020408Corrective
14 Sept 20253201000034464Corrective