GASKET,RING,12IN,600#,GR/304
Material 4100014821 · GASKET · Plant 1000
AReduceExcess
- Material
- 4100014821
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 6 FuncLocs A/B)
- Supplier
- GEMILANG LOGAM MAKMUR PT
- Lead time
- 35 d · P80 51 d
- Unit price
- Rp 115,624
Recommendation
- 1.Forecast 14 EA/year: 14 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~35 days; expected demand during lead time 1.3.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 15, order up to 29.
- 4.Stock 69 exceeds the level to keep (29) by 40.
- 5.Installed on 6 FuncLoc(s), 5 of them criticality A/B.
- 6.ML early warning: 32% probability of demand in the next 90 days.
ML early warningLast turnaround used 4Single sourceAbnormal consumption
On hand / on order
69 / 0
no open PO
Today Min / Max
3 / 10
static parameters in BoM
Rec. Min (reorder point)
15
safety stock 14
Rec. Max
29
order qty 14
Service level
100.0%
stockout risk now 0%
Unit price
Rp 115,624
PO history
ML early warning: 32% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 143 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (4 units) excluded from the baseline.
Demand pattern Lumpy · 7 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 929.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 6 functional locations
5 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1470B WASH WATER PUMP | A | 1 | 1 | 0.19 |
| PX_TCV-1871 TEMPERATURE CONTROL VALVE | B | 3 | 2 | 0.98 |
| PX_HE-256 CHARGE GAS TLE | B | 1 | 0 | 0.22 |
| PX_HE-995C FEED TLE | B | 1 | 0 | 0.22 |
| PX_PCV-499 BY PASS DUCT | B | 1 | 0 | 0.08 |
| PX_TCV-1913 PP-1160 TEMP CONTROL | C | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 35 ± 16 days (PO history + category, 2 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 08 Sept 2026 | PR03 Regular replenishment | 5 | Rp 119,306 | 26 Sept 2026 | 18 d |
| 09 Dec 2025 | PR06 Regular replenishment | 8 | Rp 111,942 | 12 Feb 2026 | 65 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Dec 2025 | Low | PX_TCV-1871 | TCV-1871; valve hunting |
| 07 Jun 2025 | Medium | PX_TCV-1871 | Leak from packing |
| 30 May 2025 | Low | PX_PP-1470B | Oil leak at PP-1470B bearing housing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 11 May 2026 | 9 | 201000016405 | Corrective |
| 20 Jan 2026 | 1 | 201000026609 | Corrective |
| 24 Dec 2025 | 4 | 203000001878 | Turnaround |
| 22 Dec 2025 | 1 | 201000038215 | Corrective |
| 21 Nov 2025 | 1 | 201000025108 | Corrective |
| 21 Sept 2025 | 3 | 201000031644 | Corrective |
| 04 Jul 2025 | 15 | 201000027911 | Corrective |
| 27 May 2025 | 5 | 201000012024 | Corrective |