GASKET,SHEET,1IN,300#,GRAPHITE

Material 4100014879 · GASKET · Plant 1000

AReduceExcess
Material
4100014879
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
31 d · P80 51 d
Unit price
Rp 214,454 (est.)

Recommendation

  • 1.Forecast 11 EA/year: 11 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~31 days; expected demand during lead time 1.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 24.
  • 4.Stock 60 exceeds the level to keep (24) by 36.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Last turnaround used 20Price estimatedLead time estimated
On hand / on order
60 / 0
no open PO
Today Min / Max
14 / 40
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 12
Rec. Max
24
order qty 12
Service level
99.9%
stockout risk now 0%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 74 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (44 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 610.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 4 functional locations

3 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1514A
RECYCLE ETHANE FLOW CONTROL
A100.11
PX_HE-1422A
METHANE CONDENSER
B121.08
PX_FCV-1886C
VD-1416A OUTLET FLOW
B400.11
PX_KT-202
TURBINE FOR KC-202
S142.81

Lead time and procurement

Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
09 Jan 2026MediumPX_KT-202KT-202 governor valve hunting
24 Dec 2025LowPX_HE-1422AHE-1422A fouling
17 Sept 2025MediumPX_KT-202Replace lamp as per PM finding
06 Jul 2025LowPX_KT-202KT-202 steam leak at gland
25 Jun 2025LowPX_HE-1422ARepair insulation HE-1422A

Recent goods issues

Posting dateQtyOrderOrder type
19 Jul 202610201000023961Corrective
03 Apr 20262201000004104Corrective
11 Dec 202518203000013324Turnaround
07 Nov 20252203000039046Turnaround
21 Aug 202524203000020904Turnaround