GASKET,SHEET,10IN,600#,PTFE
Material 4100014913 · GASKET · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100014913
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 6 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 31 d · P80 51 d
- Unit price
- Rp 214,454 (est.)
Recommendation
- 1.Forecast 38 EA/year: 38 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~31 days; expected demand during lead time 3.3.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 17, order up to 56.
- 4.On hand 6 + on order 0 is at or below the reorder point: order 50 now.
- 5.Installed on 6 FuncLoc(s), 5 of them criticality A/B.
Proposed purchase requisition
50 EA
Rp 10.7M · order by 01 Oct 2026
Expected arrival ≈ 31 days
Last turnaround used 16Price estimatedLead time estimated
On hand / on order
6 / 0
no open PO
Today Min / Max
5 / 9
static parameters in BoM
Rec. Min (reorder point)
17
safety stock 14
Rec. Max
56
order qty 39
Service level
99.9%
stockout risk now 26%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 1 days ago, 28 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (16 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 6 functional locations
5 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 4 | 114 | 42.86 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 1 | 29 | 11.58 |
| PX_KC-752A CONDENSATE BLOWER | A | 1 | 4 | 1.85 |
| PX_PP-651A BOTTOM PUMP | A | 1 | 0 | 0.19 |
| PX_HE-1813A DEMIN WATER REBOILER | B | 1 | 3 | 1.50 |
| PX_16-MS-22546-A51A-H PIPE->16 FROM VD-213 TO KC-222B | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | High | PX_HE-1813A | Cleaning HE-1813A |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 14 Sept 2026 | Low | PX_BF-105 | Install cover plate BF-105 |
| 13 Sept 2026 | Medium | PX_BF-105 | Thermograph wall BF-105 |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 06 Sept 2026 | Medium | PX_BF-105 | Repair insulation BF-105 |
| 03 Sept 2026 | Low | PX_BF-109 | Install scaffolding at BF-109 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 2 | 201000012524 | Corrective |
| 17 Feb 2026 | 4 | 204000011759 | Preventive |
| 10 Nov 2025 | 6 | 203000033996 | Turnaround |
| 10 Nov 2025 | 10 | 203000033996 | Turnaround |
| 01 Aug 2025 | 4 | 201000039898 | Corrective |