GASKET,SW,1/4IN,300#,PTFE
Material 4100014997 · GASKET · Plant 1000
ASafety-criticalReorderNormalBelow reorder point
- Material
- 4100014997
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (8 of 11 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 31 d · P80 51 d
- Unit price
- Rp 214,454 (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 20 EA/year: 20 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~31 days; expected demand during lead time 1.7.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 14, order up to 35.
- 5.On hand 2 + on order 0 is at or below the reorder point: order 33 now.
- 6.Installed on 11 FuncLoc(s), 8 of them criticality A/B.
- 7.ML early warning: 35% probability of demand in the next 90 days.
Proposed purchase requisition
33 EA
Rp 7.1M · order by 01 Oct 2026
Expected arrival ≈ 31 days
Safety-critical (SCE)ML early warningPrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
14
safety stock 13
Rec. Max
35
order qty 21
Service level
99.9%
stockout risk now 31%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 35% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 115 days ago, 14 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 11 functional locations
8 with criticality A/B · 14 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-479C DILUTION STEAM COMPRESSOR | A | 1 | 5 | 2.71 |
| PX_FCV-723 C3 RECYCLE FLOW CONTROL | A | 1 | 2 | 0.54 |
| PX_PP-1121 DILUTION STEAM PUMP | A | 1 | 2 | 0.62 |
| PX_PP-1801A DEMIN WATER PUMP | A | 1 | 1 | 0.19 |
| PX_KC-155D CAUSTIC BLOWER | A | 1 | 0 | 0.57 |
| PX_LCV-173 LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_PP-1865A METHANOL PUMP | A | 1 | 0 | 0.19 |
| PX_PRV-495C SAFETY VALVE CL-883 | A | 1 | 0 | 0.04 |
| PX_FCV-1463A PP-1775A OUTLET FLOW | C | 1 | 0 | 0.11 |
| PY_VD-1614 BFW ACCUMULATOR | C | 2 | 0 | 0.08 |
| PX_KC-773A REFLUX COMPRESSOR | S | 3 | 25 | 9.99 |
Lead time and procurement
Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 15 Sept 2026 | Low | PX_KC-773A | Install scaffolding at KC-773A |
| 10 Sept 2026 | Medium | PX_KC-479C | KC-479C bearing temp high |
| 07 Sept 2026 | Low | PX_FCV-723 | [MSI-B-26-SFU-129/M] Replace line |
| 26 Aug 2026 | Medium | PX_PP-1121 | Oil leak at PP-1121 bearing housing |
| 23 Aug 2026 | Low | PX_KC-773A | KC-773A bearing temp high |
| 18 Aug 2026 | Low | PX_KC-479C | Leak from packing |
| 10 Aug 2026 | Low | PX_KC-773A | KC-773A high vibration |
| 09 Aug 2026 | Medium | PX_KC-773A | Inspect coupling KC-773A |
| 03 Aug 2026 | Medium | PX_KC-773A | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Jun 2026 | 2 | 201000029185 | Corrective |
| 08 Jun 2026 | 1 | 201000029185 | Corrective |
| 07 Jun 2026 | 2 | 201000029185 | Corrective |
| 03 Apr 2026 | 9 | 205000024821 | Other maintenance |