Sparely
DU

GASKET,SW,3/4IN,150#,GR/304

Material 4100015050 · GASKET · Plant 1000

BReorderNormalSlow-moving
Material
4100015050
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 5 FuncLocs A/B)
Supplier
SAMUDRA SEJAHTERA PERSADA PT
Lead time
31 d · P80 51 d
Unit price
Rp 1.4M

Recommendation

  • 1.Forecast 4.5 EA/year: 4.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~31 days; expected demand during lead time 0.4.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 9.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 8 now.
  • 5.Installed on 5 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
8 EA
Rp 11.2M · order by 01 Oct 2026
Expected arrival ≈ 31 days
Single source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
9
order qty 5
Service level
99.9%
stockout risk now 17%
Unit price
Rp 1.4M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 264 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 185.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~15 days.

Installed on 5 functional locations

1 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-371B
BOTTOM FAN
B100.57
PX_HE-1008A
C3 RECYCLE CONDENSER
C100.22
PX_PP-1720D
METHANOL PUMP
C100.19
PX_KC-458D
SLOP OIL FAN
S193.14
PX_KC-365C
INHIBITOR BLOWER
S173.14

Lead time and procurement

Lead time 31 ± 16 days (PO history + category, 2 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
05 Sept 2025PR03
Regular replenishment
2Rp 1.4M26 Sept 202521 d
29 Jun 2025PR03
Regular replenishment
2Rp 1.4M08 Aug 202540 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
19 Sept 2026MediumPX_KC-458DKC-458D lube oil filter DP high
16 Sept 2026LowPX_KC-458DKC-458D lube oil filter DP high
26 Jul 2026MediumPX_KC-365CInspect coupling KC-365C
24 Jun 2026MediumPX_KC-458DKC-458D bearing temp high
15 Mar 2026MediumPX_KC-458DPainting KC-458D
27 Dec 2025MediumPX_KC-458DInstall scaffolding at KC-458D
09 Dec 2025MediumPX_KC-458DOverhaul
24 Nov 2025MediumPX_KC-458DKC-458D lube oil filter DP high
18 Nov 2025MediumPX_KC-365CInstall scaffolding at KC-365C

Recent goods issues

Posting dateQtyOrderOrder type
10 Jan 20262201000025650Corrective