GASKET,RING,3/4IN,300#,PTFE

Material 4100015148 · GASKET · Plant 1000

AReorderCriticalBelow reorder point
Material
4100015148
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (7 of 7 FuncLocs A/B)
Supplier
No PO history
Lead time
31 d · P80 51 d
Unit price
Rp 214,454 (est.)

Recommendation

  • 1.Forecast 59 EA/year: 59 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~31 days; expected demand during lead time 5.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 24, order up to 84.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 82 now.
  • 5.Installed on 7 FuncLoc(s), 7 of them criticality A/B.
Proposed purchase requisition
82 EA
Rp 17.6M · order by 01 Oct 2026
Expected arrival ≈ 31 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
24
safety stock 19
Rec. Max
84
order qty 60
Service level
100.0%
stockout risk now 72%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 19% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 70 days ago, 23 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 7 functional locations

7 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-112
CRACKING FURNACE BF-112
A17327.01
PX_BF-109
CRACKING FURNACE BF-109
A12911.58
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_HE-1372D
INHIBITOR COOLER
B131.08
PX_PP-1577D
ETHYLENE PUMP
B121.05

Lead time and procurement

Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
21 Sept 2026LowPX_KC-717Leak from packing
20 Sept 2026MediumPX_BF-109Thermograph wall BF-109
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112
13 Sept 2026MediumPX_BF-109Install scaffolding at BF-109
07 Sept 2026MediumPX_PP-1577DReplace bearing PP-1577D
04 Sept 2026HighPX_BF-112Install scaffolding at BF-112
03 Sept 2026LowPX_BF-109Install scaffolding at BF-109

Recent goods issues

Posting dateQtyOrderOrder type
23 Jul 20264201000031020Corrective