GASKET,RING,8IN,150#,PTFE

Material 4100015150 · GASKET · Plant 1000

AReduceExcess
Material
4100015150
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (6 of 7 FuncLocs A/B)
Supplier
No PO history
Lead time
31 d · P80 51 d
Unit price
Rp 214,454 (est.)

Recommendation

  • 1.Forecast 4.2 EA/year: 3.5 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~31 days; expected demand during lead time 0.3.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 15.
  • 4.Stock 66 exceeds the level to keep (15) by 51.
  • 5.Installed on 7 FuncLoc(s), 6 of them criticality A/B.
Last turnaround used 10Price estimatedLead time estimated
On hand / on order
66 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 10
Rec. Max
15
order qty 5
Service level
100.0%
stockout risk now 0%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 112 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (10 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 226.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 7 functional locations

6 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-106
TEMPERATURE CONTROL VALVE
A110.12
PX_KC-223
RECYCLE ETHANE FAN
A100.57
PX_LCV-832D
LEVEL CONTROL VALVE
A100.12
PX_VD-855B
QUENCH OIL SEPARATOR
A100.08
PX_PCV-1362
VD-219 PRESSURE CONTROL
B100.08
PX_PP-615A
PROPYLENE PUMP
B100.19
PX_VD-1889
BOTTOM KO DRUM
S100.08

Lead time and procurement

Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Jan 2027PX_PP-615APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 May 2025MediumPX_TCV-106Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
11 Jun 20265201000038887Corrective
19 Nov 202510203000006868Turnaround