GASKET,RING,3IN,600#,PTFE
Material 4100015184 · GASKET · Plant 1000
ASafety-criticalMonitorCritical insurance spare
- Material
- 4100015184
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 6 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 31 d · P80 51 d
- Unit price
- Rp 214,454 (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 1.3 EA/year: 0.6 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 3.Lead time ~31 days; expected demand during lead time 0.8 (incl. 0.7 planned).
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
Safety-critical (SCE)Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
5 / 9
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
100.0%
stockout risk now 0%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 61.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 6 functional locations
4 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-235D DEMIN WATER FAN | A | 1 | 2 | 1.00 |
| PX_HE-1455C COOLING WATER COOLER | A | 1 | 1 | 0.22 |
| PX_HE-1481 CAUSTIC COOLER | A | 1 | 0 | 0.22 |
| PX_CL-721 QUENCH OIL SCRUBBER | B | 1 | 6 | 2.09 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
| PX_SDV-289A BOTTOM ISOLATION | S | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_KC-235D | Compressor major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Jul 2026 | High | PX_CL-721 | CL-721 DP high |
| 07 Feb 2026 | Medium | PX_CL-721 | Install scaffolding at CL-721 |
| 15 Jan 2026 | Low | PX_CL-721 | CL-721 DP high |
| 28 Nov 2025 | High | PX_CL-721 | Inspect CL-721 internal |
| 11 Nov 2025 | Medium | PX_KC-235D | Leak from packing |
| 21 Oct 2025 | Medium | PX_CL-721 | Leak from packing |
| 17 May 2025 | Medium | PX_CL-721 | Replace lamp as per PM finding |
| 16 May 2025 | Low | PX_KC-235D | Leak from packing |
| 04 May 2025 | Medium | PX_HE-1455C | PSM25/Cleaning HE-1455C |
Recent goods issues
Never issued in the 17-month history.