GASKET,SHEET,12IN,600#,GRAPHITE
Material 4100015363 · GASKET · Plant 1000
AReduceNon-moving
- Material
- 4100015363
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA PERSADA PT
- Lead time
- 35 d · P80 51 d
- Unit price
- Rp 1.3M
Recommendation
- 1.Forecast 1.5 EA/year: 1.5 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~35 days; expected demand during lead time 0.1.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
- 4.Stock 15 exceeds the level to keep (8) by 7.
- 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Single source
On hand / on order
15 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.3M
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 146.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 4 functional locations
2 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_VD-1149 SPENT CAUSTIC SURGE DRUM | A | 1 | 4 | 0.93 |
| PX_HE-397 SEAL OIL COOLER | A | 1 | 0 | 0.22 |
| PX_6-HS-10663-A22A-H PIPE-6 FROM KC-155D TO PP-800 | C | 1 | 0 | 0.01 |
| PX_KC-773A REFLUX COMPRESSOR | S | 1 | 25 | 9.99 |
Lead time and procurement
Lead time 35 ± 16 days (PO history + category, 2 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 17 May 2026 | PR03 Regular replenishment | 1 | Rp 1.3M | 11 Jun 2026 | 25 d |
| 13 Jun 2025 | PR03 Regular replenishment | 2 | Rp 1.3M | 11 Aug 2025 | 59 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 15 Sept 2026 | Low | PX_KC-773A | Install scaffolding at KC-773A |
| 23 Aug 2026 | Low | PX_KC-773A | KC-773A bearing temp high |
| 10 Aug 2026 | Low | PX_KC-773A | KC-773A high vibration |
| 09 Aug 2026 | Medium | PX_KC-773A | Inspect coupling KC-773A |
| 03 Aug 2026 | Medium | PX_KC-773A | Leak from packing |
| 20 Jul 2026 | Medium | PX_KC-773A | KC-773A high vibration |
| 13 Jul 2026 | Low | PX_KC-773A | KC-773A lube oil filter DP high |
| 07 Jul 2026 | Medium | PX_KC-773A | KC-773A lube oil filter DP high |
| 03 Jul 2026 | Medium | PX_KC-773A | Leak from packing |
Recent goods issues
Never issued in the 17-month history.