GASKET,RING,1-1/2IN,600#,PTFE

Material 4100015375 · GASKET · Plant 1000

ASafety-criticalMonitorSlow-moving
Material
4100015375
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (7 of 11 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
PRIMA UTAMA PRATAMA PT
Lead time
29 d · P80 51 d
Unit price
Rp 101,928

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 3.9 EA/year: 3.9 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~29 days; expected demand during lead time 0.3.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
  • 5.Installed on 11 FuncLoc(s), 7 of them criticality A/B.
Safety-critical (SCE)Single sourceOpen PO
On hand / on order
6 / 2
next delivery 01 Oct 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
99.9%
stockout risk now 0%
Unit price
Rp 101,928
PO history
ML early warning: 29% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 261 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 624.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 11 functional locations

7 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-778A
CONDENSATE COMPRESSOR
A131.43
PY_HE-1907A
METHANE TLE
A131.08
PX_PCV-1570
HE-846B PRESSURE CONTROL
A120.51
PX_HE-1305B
FEED CONDENSER
A110.22
PX_LCV-1581
LEVEL CONTROL VALVE
A110.12
PX_PP-413
C3 RECYCLE PUMP
B172.76
PX_PP-681B
FEED PUMP
B100.19
PX_FCV-559
C3 RECYCLE FLOW CONTROL
C100.11
PX_PCV-1135
PP-1811A PRESSURE CONTROL
C100.08
PX_PRV-575
SAFETY VALVE HE-1537D
S110.04
PX_PRV-610
SAFETY VALVE PP-129D
S100.04

Lead time and procurement

Lead time 29 ± 16 days (PO history + category, 2 PO lines) · on-time 48%

PR dateTypeQtyUnit priceDeliveryLead time
04 Sept 2026PR03
Regular replenishment
2Rp 99,80701 Oct 2026
open
27 d
13 Oct 2025PR03
Regular replenishment
2Rp 104,04906 Nov 202524 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
06 Jun 2026MediumPX_PP-413PP-413 discharge pressure low
04 Jun 2026HighPX_KC-778AInspect coupling KC-778A
26 May 2026MediumPX_PP-413PP-413 high vibration
30 Apr 2026LowPX_PP-413Replace lamp as per PM finding
30 Mar 2026LowPX_PP-413[MSI-B-26-ECN-211/M] Replace line
10 Dec 2025MediumPX_PCV-1570Install scaffolding at PCV-1570
03 Dec 2025LowPX_PP-413PP-413 high vibration
11 Nov 2025LowPY_HE-1907ALeak from packing
05 Nov 2025MediumPX_KC-778AKC-778A lube oil filter DP high
03 Sept 2025MediumPY_HE-1907ACleaning HE-1907A

Recent goods issues

Posting dateQtyOrderOrder type
13 Jan 20261201000029999Corrective
16 Nov 20253201000006164Corrective