GASKET,SHEET,8IN,300#,GRAPHITE
Material 4100015613 · GASKET · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100015613
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 31 d · P80 51 d
- Unit price
- Rp 214,454 (est.)
Recommendation
- 1.Forecast 2.0 EA/year: 1.3 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~31 days; expected demand during lead time 0.8 (incl. 0.7 planned).
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 4 now.
- 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 857,815 · order by 01 Oct 2026
Expected arrival ≈ 31 days
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
100.0%
stockout risk now 1%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 417.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 5 functional locations
2 with criticality A/B · 11 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-235D DEMIN WATER FAN | A | 1 | 2 | 1.00 |
| PX_MOV-731A MOTOR OPERATED GATE VALVE | B | 1 | 0 | 0.06 |
| PX_HE-1396C PROPYLENE TLE | C | 4 | 7 | 2.79 |
| PX_HE-593C REFLUX REBOILER | C | 4 | 1 | 0.22 |
| PY_HE-235A DEMIN WATER CONDENSER | C | 1 | 1 | 0.22 |
Lead time and procurement
Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_KC-235D | Compressor major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 17 Sept 2026 | Medium | PX_HE-1396C | [MSI-B-26-NWH-385] Permanent repair |
| 15 Jun 2026 | Medium | PX_HE-1396C | [MSI-B-26-DDD-161] Permanent repair |
| 22 Apr 2026 | Low | PX_HE-1396C | Retubing HE-1396C |
| 03 Apr 2026 | High | PX_HE-1396C | Cleaning HE-1396C |
| 10 Feb 2026 | Medium | PX_HE-1396C | HE-1396C fouling |
| 11 Nov 2025 | Medium | PX_KC-235D | Leak from packing |
| 07 Nov 2025 | Medium | PX_HE-1396C | Leak from packing |
| 13 Aug 2025 | Medium | PX_HE-593C | Install scaffolding at HE-593C |
| 28 May 2025 | Medium | PY_HE-235A | PSM25/HE-235A tube leak |
| 16 May 2025 | Low | PX_KC-235D | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 06 May 2025 | 1 | 201000012283 | Corrective |