Sparely
DU

GASKET,RING,10IN,150#,GR/304

Material 4100015840 · GASKET · Plant 1000

AMonitorSlow-moving
Material
4100015840
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
31 d · P80 51 d
Unit price
Rp 214,454 (est.)

Recommendation

  • 1.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~31 days; expected demand during lead time 0.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 486 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 112.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_CL-1039
CHARGE GAS STRIPPER
A120.81
PX_TCV-1344
TEMPERATURE CONTROL VALVE
A110.12

Lead time and procurement

Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 May 2026MediumPX_CL-1039CL-1039 DP high
27 May 2025HighPX_TCV-1344TCV-1344; small leak at packing
24 May 2025LowPX_CL-1039Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
02 Jun 20251201000016309Corrective