GASKET,RING,1/4IN,150#,GR/304

Material 4100015941 · GASKET · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100015941
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
No PO history
Lead time
31 d · P80 51 d
Unit price
Rp 214,454 (est.)

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 6.4 EA/year: 6.4 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~31 days; expected demand during lead time 0.5.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 17.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 17 now.
  • 6.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
17 EA
Rp 3.6M · order by 01 Oct 2026
Expected arrival ≈ 31 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 10
Rec. Max
17
order qty 7
Service level
100.0%
stockout risk now 10%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 98 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 410.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 4 functional locations

3 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-178A
QUENCH OIL FAN
A100.57
PX_PCV-1103
PRESSURE CONTROL VALVE
B130.51
PX_PP-1939
BFW PUMP
B100.19
PX_PRV-868
SAFETY VALVE VD-1167
S100.04

Lead time and procurement

Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Jun 2026MediumPX_PCV-1103PCV-1103; IA leak from regulator
29 Sept 2025MediumPX_PCV-1103Install scaffolding at PCV-1103
09 May 2025MediumPX_PCV-1103[MSI-B-25-XXZ-362/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
25 Jun 20264201000038239Corrective
24 Apr 20266204000001034Preventive