GASKET,RING,1-1/2IN,150#,GRAPHITE

Material 4100015946 · GASKET · Plant 1000

AReduceSlow-moving
Material
4100015946
Category
GASKET
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
RAJAWALI SARANA SENTOSA PT
Lead time
34 d · P80 51 d
Unit price
Rp 250,288

Recommendation

  • 1.Forecast 1.8 EA/year: 1.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~34 days; expected demand during lead time 0.2.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.Stock 12 exceeds the level to keep (6) by 6.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Single source
On hand / on order
12 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 250,288
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 274 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 293.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 3 functional locations

2 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-902B
BFW PUMP
A482.33
PX_LCV-303
VD-1035D LEVEL CONTROL
A100.12
PX_VD-999
ETHYLENE ACCUMULATOR
C100.08

Lead time and procurement

Lead time 34 ± 16 days (PO history + category, 1 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
17 Sept 2025PR06
Regular replenishment
1Rp 250,28831 Oct 202544 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Jul 2026LowPX_PP-902BReplace lamp as per PM finding
02 Mar 2026MediumPX_PP-902BInstall scaffolding at PP-902B
26 Feb 2026MediumPX_PP-902BInstall cover plate for MCP cracking
26 Nov 2025HighPX_PP-902BPP-902B abnormal noise
15 Oct 2025MediumPX_PP-902BInstall scaffolding at PP-902B
22 Sept 2025HighPX_PP-902BRepair insulation PP-902B
04 Sept 2025MediumPX_PP-902B[MSI-B-25-WCE-184] Permanent repair
04 May 2025MediumPX_PP-902BPP-902B seal leak

Recent goods issues

Posting dateQtyOrderOrder type
31 Dec 20252201000033177Corrective