GASKET,RING,1IN,600#,GR/304
Material 4100016059 · GASKET · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100016059
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 6 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 31 d · P80 51 d
- Unit price
- Rp 214,454 (est.)
Recommendation
- 1.Forecast 0.7 EA/year: 0.7 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~31 days; expected demand during lead time 0.1.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 6 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
100.0%
stockout risk now 2%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 70.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 6 functional locations
2 with criticality A/B · 12 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-752A CONDENSATE BLOWER | A | 4 | 4 | 1.85 |
| PX_PP-169A QUENCH OIL PUMP | B | 3 | 5 | 1.90 |
| PX_FCV-1386 BY PASS LINE | C | 1 | 2 | 0.54 |
| PX_8-CW-21089-A51A-C PIPE-8 FROM PP-128C TO PP-319 | C | 1 | 0 | 0.01 |
| PX_KC-984C CONDENSATE COMPRESSOR | S | 2 | 2 | 1.00 |
| PX_MOV-220 MOTOR OPERATED GATE VALVE | S | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Jul 2026 | Medium | PX_PP-169A | Install cover plate for MCP cracking |
| 25 Jun 2026 | Medium | PX_PP-169A | PP-169A seal leak |
| 19 Jun 2026 | Medium | PX_FCV-1386 | FCV-1386 passing |
| 05 Apr 2026 | Medium | PX_PP-169A | Overhaul PP-169A |
| 20 Dec 2025 | Medium | PX_PP-169A | Overhaul PP-169A |
| 10 Dec 2025 | Medium | PX_KC-752A | Replace lamp as per PM finding |
| 18 Oct 2025 | Medium | PX_KC-752A | Replace lamp as per PM finding |
| 21 Sept 2025 | Low | PX_KC-752A | Overhaul |
| 05 Sept 2025 | Medium | PX_KC-984C | Overhaul |
| 30 May 2025 | Low | PX_KC-984C | Inspect coupling KC-984C |
Recent goods issues
Never issued in the 17-month history.