GASKET,SHEET,3IN,150#,GR/304
Material 4100016423 · GASKET · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100016423
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 4 FuncLocs A/B)
- Supplier
- NUSA ELEKTRIK SENTOSA PT
- Lead time
- 25 d · P80 51 d
- Unit price
- Rp 2.2M
Recommendation
- 1.Forecast 6.0 EA/year: 5.3 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~25 days; expected demand during lead time 0.4.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 11.
- 4.On hand 3 + on order 0 is at or below the reorder point: order 8 now.
- 5.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
8 EA
Rp 17.3M · order by 01 Oct 2026
Expected arrival ≈ 25 days
Single source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
11
order qty 7
Service level
99.6%
stockout risk now 9%
Unit price
Rp 2.2M
PO history
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 114 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 425.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 4 functional locations
1 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-574B INHIBITOR TLE | A | 4 | 0 | 0.22 |
| PX_8-P-21146-A41A-T PIPE-8 FROM VD-884 TO PP-1752A | C | 1 | 1 | 0.01 |
| PX_LCV-1953 HE-1441D LEVEL CONTROL | C | 2 | 1 | 0.12 |
| PX_KT-264A TURBINE FOR KC-264A | S | 1 | 4 | 2.39 |
Lead time and procurement
Lead time 25 ± 16 days (PO history + category, 2 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 06 Jul 2026 | PR03 Regular replenishment | 4 | Rp 2.2M | 15 Jul 2026 | 9 d |
| 30 Dec 2025 | PR03 Regular replenishment | 3 | Rp 2.1M | 21 Jan 2026 | 22 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 21 Apr 2026 | Low | PX_KT-264A | Follow up after steam upset KT-264A |
| 21 Oct 2025 | Medium | PX_KT-264A | KT-264A governor valve hunting |
| 31 May 2025 | Medium | PX_KT-264A | Install scaffolding at KT-264A |
| 22 May 2025 | Low | PX_8-P-21146-A41A-T | Leak at 8-P-21146-A41A-T |
| 10 May 2025 | Medium | PX_LCV-1953 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 09 Jun 2026 | 4 | 201000006748 | Corrective |
| 16 Oct 2025 | 4 | 201000025573 | Corrective |