GASKET,SHEET,4IN,150#,PTFE

Material 4100016866 · GASKET · Plant 1000

ASafety-criticalReduceSlow-moving
Material
4100016866
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 2 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
GEMILANG LOGAM MAKMUR PT
Lead time
28 d · P80 27 d
Unit price
Rp 804,190

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.7 EA/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~28 days; expected demand during lead time 0.1.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 5.Stock 13 exceeds the level to keep (4) by 9.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Single source
On hand / on order
13 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 804,190
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 353 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 105.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-995
SAFETY VALVE PP-1830B
A120.47
PX_PP-1797
CHARGE GAS PUMP
A100.19

Lead time and procurement

Lead time 28 ± 9 days (PO history, 3 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
29 Sept 2025PR03
Regular replenishment
2Rp 804,19023 Oct 202524 d
29 Jul 2025PR03
Regular replenishment
1Rp 789,04224 Aug 202526 d
16 Jul 2025PR03
Regular replenishment
2Rp 828,64712 Aug 202527 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
10 Oct 2025MediumPX_PRV-995Replace lamp as per PM finding
16 May 2025MediumPX_PRV-995Recertification PRV-995

Recent goods issues

Posting dateQtyOrderOrder type
13 Oct 20252204000000302Preventive