GASKET,RING,6IN,150#,GRAPHITE

Material 4100016925 · GASKET · Plant 1000

AReduceNon-moving
Material
4100016925
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
SAMUDRA SEJAHTERA INTERNASIONAL PT
Lead time
27 d · P80 51 d
Unit price
Rp 217,193

Recommendation

  • 1.Forecast 0.2 EA/year: 0.2 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~27 days; expected demand during lead time 0.0.
  • 3.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 4.
  • 4.Stock 28 exceeds the level to keep (4) by 24.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Single source
On hand / on order
28 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
4
order qty 4
Service level
99.4%
stockout risk now 0%
Unit price
Rp 217,193
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 24.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-222B
LEAN AMINE COMPRESSOR
A151.85

Lead time and procurement

Lead time 27 ± 16 days (PO history + category, 1 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
30 May 2025PR03
Regular replenishment
2Rp 217,19314 Jun 202515 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
02 Jul 2026HighPX_KC-222BReplace lamp as per PM finding
05 Feb 2026MediumPX_KC-222BInstall scaffolding at KC-222B
01 Jan 2026LowPX_KC-222BKC-222B high vibration
16 Nov 2025MediumPX_KC-222BKC-222B lube oil filter DP high
17 May 2025LowPX_KC-222BInstall scaffolding at KC-222B

Recent goods issues

Never issued in the 17-month history.