GASKET,SW,1-1/2IN,150#,GRAPHITE

Material 4100017013 · GASKET · Plant 1000

BReduceNon-moving
Material
4100017013
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
B (2 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
31 d · P80 51 d
Unit price
Rp 214,454 (est.)

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~31 days; expected demand during lead time 0.0.
  • 3.A 98.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 4.
  • 4.Stock 5 exceeds the level to keep (4) by 1.
  • 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
4 / 7
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
4
order qty 4
Service level
98.9%
stockout risk now 0%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 10.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~15 days.

Installed on 4 functional locations

2 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-483B
LEAN AMINE PUMP
B151.90
PX_HE-495C
CAUSTIC TLE
B100.22
PX_HE-1547C
DEMIN WATER PREHEATER
C130.65
PX_BF-102-PD10
COIL OUTLET BF-102
C100.45

Lead time and procurement

Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Aug 2026MediumPX_PP-483BPP-483B abnormal noise
29 Jun 2026MediumPX_PP-483BOil leak at PP-483B bearing housing
06 May 2026MediumPX_HE-1547C[MSI-B-26-ZAH-285] Permanent repair
18 Nov 2025MediumPX_PP-483BLeak from packing
18 Nov 2025MediumPX_PP-483BReplace lamp as per PM finding
08 Nov 2025MediumPX_HE-1547CInstall scaffolding at HE-1547C
24 May 2025MediumPX_PP-483BInstall scaffolding at PP-483B
22 May 2025MediumPX_HE-1547CHE-1547C tube leak

Recent goods issues

Never issued in the 17-month history.