GASKET,RING,10IN,300#,GR/304
Material 4100017089 · GASKET · Plant 1000
AReduceExcess
- Material
- 4100017089
- Category
- GASKET
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- KARYA UTAMA GLOBAL PT
- Lead time
- 24 d · P80 51 d
- Unit price
- Rp 38,617
Recommendation
- 1.Forecast 10 EA/year: 10 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~24 days; expected demand during lead time 0.7.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 11, order up to 22.
- 4.Stock 25 exceeds the level to keep (22) by 3.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Convert to Stock ItemSingle source
On hand / on order
25 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
11
safety stock 11
Rec. Max
22
order qty 11
Service level
100.0%
stockout risk now 0%
Unit price
Rp 38,617
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 80 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 599.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-536A LUBE OIL BLOWER | A | 1 | 11 | 4.42 |
Lead time and procurement
Lead time 24 ± 16 days (PO history + category, 2 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 Feb 2026 | PR06 Regular replenishment | 4 | Rp 38,099 | 08 Mar 2026 | 20 d |
| 20 Dec 2025 | PR03 Regular replenishment | 3 | Rp 39,134 | 28 Dec 2025 | 8 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | High | PX_KC-536A | Overhaul |
| 08 Aug 2026 | High | PX_KC-536A | KC-536A bearing temp high |
| 24 Jul 2026 | High | PX_KC-536A | Install scaffolding at KC-536A |
| 05 Jul 2026 | Medium | PX_KC-536A | Leak from packing |
| 24 Jun 2026 | Medium | PX_KC-536A | KC-536A bearing temp high |
| 31 Mar 2026 | Medium | PX_KC-536A | Install scaffolding at KC-536A |
| 18 Jan 2026 | Low | PX_KC-536A | Replace lamp as per PM finding |
| 10 Jan 2026 | Low | PX_KC-536A | KC-536A bearing temp high |
| 17 Nov 2025 | Medium | PX_KC-536A | Overhaul |
| 08 Nov 2025 | Medium | PX_KC-536A | Inspect coupling KC-536A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 13 Jul 2026 | 7 | 201000001615 | Corrective |
| 30 Jan 2026 | 4 | 201000036633 | Corrective |