Sparely
DU

GASKET,SHEET,4IN,300#,PTFE

Material 4100017368 · GASKET · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100017368
Category
GASKET
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 2 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
GUNUNG SARANA SENTOSA PT
Lead time
25 d · P80 24 d
Unit price
Rp 3.0M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~25 days; expected demand during lead time 0.1.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 11.8M · order by 01 Oct 2026
Expected arrival ≈ 25 days
Safety-critical (SCE)Convert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
99.9%
stockout risk now 4%
Unit price
Rp 3.0M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 146 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 217.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 2 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_HE-1200D
REFLUX PREHEATER
A100.22
PX_PRV-1866D
SAFETY VALVE PP-506A
S100.04

Lead time and procurement

Lead time 25 ± 13 days (PO history, 3 PO lines) · on-time 45%

PR dateTypeQtyUnit priceDeliveryLead time
06 Mar 2026PR05
Project / turnaround
1Rp 3.0M01 Apr 202626 d
22 Nov 2025PR06
Regular replenishment
1Rp 3.1M30 Nov 20258 d
10 Aug 2025PR03
Regular replenishment
2Rp 2.9M01 Sept 202522 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
08 May 20262201000028932Corrective
29 Jul 20251201000012996Corrective
Sparely