GASKET,SW,1/2IN,150#,PTFE
Material 4100017775 · GASKET · Plant 1000
AMonitorInsurance gap
- Material
- 4100017775
- Category
- GASKET
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 31 d · P80 51 d
- Unit price
- Rp 214,454 (est.)
Recommendation
- 1.Forecast 4.7 EA/year: 4.7 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~31 days; expected demand during lead time 0.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 12.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
5 / 7
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 7
Rec. Max
12
order qty 5
Service level
100.0%
stockout risk now 11%
Unit price
Rp 214,454
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 23 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 459.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 3 functional locations
2 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-104-BRN08 COIL OUTLET BF-104 | A | 1 | 2 | 1.30 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
Lead time and procurement
Lead time 31 ± 16 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 19 Sept 2026 | Medium | PX_BF-106 | Cleaning burner BF-106 |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 15 Sept 2026 | Medium | PX_BF-106 | Install cover plate BF-106 |
| 14 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 10 Sept 2026 | Medium | PX_BF-106 | Replace burner tip BF-106 |
| 08 Sept 2026 | Low | PX_BF-106 | Leak from packing |
| 08 Sept 2026 | Medium | PX_BF-106 | Painting BF-106 |
Recent goods issues
Never issued in the 17-month history.