GASKET,SW,6IN,150#,PTFE

Material 4100018944 · GASKET · Plant 1000

CMonitorSlow-moving
Material
4100018944
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 4 FuncLocs A/B)
Supplier
RAJAWALI INSTRUMEN INTERNASIONAL PT
Lead time
34 d · P80 51 d
Unit price
Rp 654,088

Recommendation

  • 1.Forecast 3.5 EA/year: 3.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~34 days; expected demand during lead time 0.3.
  • 3.A 97.3% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 12.
Single source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
12
order qty 12
Service level
97.3%
stockout risk now 3%
Unit price
Rp 654,088
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 291 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~15 days.

Installed on 4 functional locations

0 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_HE-1579D
SPENT CAUSTIC PREHEATER
C210.22
PX_FCV-1797
CONTROL VALVE
C100.11
PX_ROF-545
RESTRICTION ORIFICE
C100.00
PX_PCV-538
HE-876B PRESSURE CONTROL
S100.08

Lead time and procurement

Lead time 34 ± 16 days (PO history + category, 1 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
06 Sept 2025PR01
Import / long-lead
2Rp 654,08820 Oct 202544 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
10 May 2025MediumPX_HE-1579D[MSI-B-25-RCD-299/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
14 Dec 20257201000017345Corrective
14 Dec 20255201000032995Corrective