O-RING,NBR,41MM ID,5.3MM CS
Material 4100019326 · O-RING · Plant 1000
ASafety-criticalMonitorHealthy
- Material
- 4100019326
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (71 of 110 FuncLocs A/B, 21 safety/shutdown valve)
- Supplier
- TIRTA SUPLINDO LESTARI PT
- Lead time
- 20 d · P80 27 d
- Unit price
- Rp 52,126
Recommendation
- 1.Safety-critical element: installed on 21 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 393 EA/year: 389 unplanned (recency-weighted compound poisson (own history)) + 3.6 from the maintenance plan.
- 3.Lead time ~20 days; expected demand during lead time 22.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 71, order up to 408.
- 5.Installed on 110 FuncLoc(s), 71 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 68Single sourceAbnormal consumptionOpen PO
On hand / on order
62 / 330
next delivery 13 Oct 2026
Today Min / Max
34 / 89
static parameters in BoM
Rec. Min (reorder point)
71
safety stock 50
Rec. Max
408
order qty 337
Service level
99.9%
stockout risk now 0%
Unit price
Rp 52,126
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 34 issue days in the last 180 days, last issue 1 days ago, 64 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 17 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (114 units) excluded from the baseline.
Demand pattern Smooth · 136 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 25.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 110 functional locations
71 with criticality A/B · 146 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_KC-419A PROPYLENE FAN | A | 1 | 19 | 5.71 |
| PX_KC-536A LUBE OIL BLOWER | A | 1 | 11 | 4.42 |
| PX_PP-1776B RICH AMINE PUMP | A | 1 | 8 | 3.62 |
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_PP-790A CHARGE GAS PUMP | A | 1 | 7 | 2.76 |
| PX_KC-226 HYDROGEN AIR COMPRESSOR | A | 1 | 6 | 2.28 |
| PX_KC-308B REFLUX BLOWER | A | 1 | 6 | 2.28 |
| PX_KC-732D METHANOL COMPRESSOR | A | 1 | 6 | 3.14 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_PP-1970 FEED PUMP | A | 1 | 6 | 1.47 |
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 1 | 5 | 1.85 |
| PX_KC-316D METHANOL FAN | A | 1 | 5 | 1.43 |
Lead time and procurement
Lead time 20 ± 9 days (PO history, 45 PO lines) · on-time 40%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 Sept 2026 | PR03 Regular replenishment | 330 | Rp 50,558 | 13 Oct 2026 open | 29 d |
| 31 Aug 2026 | PR03 Regular replenishment | 207 | Rp 51,521 | 17 Sept 2026 | 17 d |
| 22 Aug 2026 | PR03 Regular replenishment | 263 | Rp 53,161 | 07 Sept 2026 | 16 d |
| 20 Aug 2026 | PR06 Regular replenishment | 208 | Rp 50,841 | 30 Aug 2026 | 10 d |
| 10 Aug 2026 | PR03 Regular replenishment | 378 | Rp 50,991 | 25 Sept 2026 | 46 d |
| 08 Aug 2026 | PR05 Project / turnaround | 320 | Rp 52,909 | 30 Aug 2026 | 22 d |
| 10 Jul 2026 | PR04 Regular (other) | 259 | Rp 53,127 | 30 Jul 2026 | 20 d |
| 30 Jun 2026 | PR06 Regular replenishment | 134 | Rp 50,051 | 11 Jul 2026 | 11 d |
| 16 Jun 2026 | PR03 Regular replenishment | 124 | Rp 51,991 | 30 Jun 2026 | 14 d |
| 06 Jun 2026 | PR06 Regular replenishment | 169 | Rp 54,462 | 30 Jun 2026 | 24 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
| 02 Feb 2027 | PX_PP-376A | Pump overhaul | 0.72 |
| 02 Jun 2027 | PX_PP-1970 | Pump overhaul | 0.72 |
| 01 Aug 2027 | PX_KC-620A | Compressor major overhaul | 0.72 |
| 02 Aug 2027 | PX_PP-536 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Low | PX_KC-886D | KC-886D high vibration |
| 28 Sept 2026 | High | PY_KC-419A | Overhaul |
| 26 Sept 2026 | Medium | PX_KC-396 | Replace lamp as per PM finding |
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 24 Sept 2026 | Emergency | PX_KC-538 | KC-538 high vibration |
| 24 Sept 2026 | Emergency | PX_PP-410 | Install cover plate for MCP cracking |
| 23 Sept 2026 | Medium | PX_KC-513 | KC-513 high vibration |
| 23 Sept 2026 | Medium | PX_PP-790A | PP-790A abnormal noise |
| 23 Sept 2026 | Medium | PY_KC-419A | Inspect coupling KC-419A |
| 22 Sept 2026 | High | PX_KC-536A | Overhaul |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 8 | 201000012524 | Corrective |
| 23 Sept 2026 | 2 | 209000029477 | Other maintenance |
| 10 Sept 2026 | 6 | 201000015119 | Corrective |
| 10 Sept 2026 | 4 | 201000021470 | Corrective |
| 10 Sept 2026 | 1 | 204000008119 | Preventive |
| 26 Aug 2026 | 1 | 201000038696 | Corrective |
| 05 Aug 2026 | 3 | 204000027988 | Preventive |
| 02 Aug 2026 | 1 | 201000026506 | Corrective |
| 23 Jul 2026 | 2 | 201000024568 | Corrective |
| 17 Jul 2026 | 1 | 201000011960 | Corrective |
| 16 Jul 2026 | 9 | 201000011801 | Corrective |
| 15 Jul 2026 | 5 | 201000020061 | Corrective |
| 10 Jul 2026 | 1 | 201000002156 | Corrective |
| 08 Jul 2026 | 6 | 201000029459 | Corrective |
| 05 Jul 2026 | 6 | 201000037602 | Corrective |