O-RING,VITON,263MM ID,2.5MM CS

Material 4100019402 · O-RING · Plant 1000

ASafety-criticalMonitorHealthy
Material
4100019402
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (13 of 20 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
MEGA UTAMA GLOBAL PT
Lead time
42 d · P80 69 d
Unit price
Rp 73,747

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 92 EA/year: 90 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 3.Lead time ~42 days; expected demand during lead time 10.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 41, order up to 133.
  • 5.Installed on 20 FuncLoc(s), 13 of them criticality A/B.
  • 6.ML early warning: 100% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 46Single sourceAbnormal consumption
On hand / on order
48 / 0
no open PO
Today Min / Max
18 / 53
static parameters in BoM
Rec. Min (reorder point)
41
safety stock 31
Rec. Max
133
order qty 92
Service level
99.9%
stockout risk now 0%
Unit price
Rp 73,747
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 12 issue days in the last 180 days, last issue 1 days ago, 16 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 9 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (46 units) excluded from the baseline.

Demand pattern Erratic · 40 issue days · 5 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 20 functional locations

13 with criticality A/B · 20 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-247A
SLOP OIL FAN
A194.00
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_PP-818
LUBE OIL PUMP
A161.90
PX_KC-317B
RICH AMINE FAN
A141.85
PX_KC-396
WASH WATER BLOWER
A131.43
PX_PP-1769A
LUBE OIL PUMP
A130.19
PX_PP-417
GASOLINE PUMP
A130.62
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_PP-1599A
SLOP OIL PUMP
B151.90
PX_PP-1397
METHANOL PUMP
B141.05
PX_SDV-459B
HE-132D SHUTDOWN VALVE
B130.91

Lead time and procurement

Lead time 42 ± 26 days (PO history, 16 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
28 Aug 2026PR06
Regular replenishment
73Rp 76,78716 Sept 202619 d
12 Aug 2026PR06
Regular replenishment
77Rp 75,23504 Sept 202623 d
23 Jul 2026PR03
Regular replenishment
65Rp 76,92716 Sept 202655 d
14 Jul 2026PR03
Regular replenishment
94Rp 72,40308 Sept 202656 d
30 Jun 2026PR06
Regular replenishment
84Rp 72,51614 Jul 202614 d
23 May 2026PR03
Regular replenishment
75Rp 77,04004 Jun 202612 d
18 May 2026PR03
Regular replenishment
86Rp 74,41715 Jun 202628 d
14 May 2026PR03
Regular replenishment
57Rp 72,36422 Jul 202669 d
24 Apr 2026PR03
Regular replenishment
90Rp 75,78011 Jul 202678 d
28 Mar 2026PR03
Regular replenishment
48Rp 73,62129 Apr 202632 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
13 Aug 2027PX_PP-1397Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
05 Sept 2026MediumPX_PP-1599APP-1599A abnormal noise
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
27 Aug 2026HighPX_KC-247AInspect coupling KC-247A
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
20 Aug 2026LowPX_PP-1397Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
30 Sept 20265201000025027Corrective
26 Sept 20266201000005010Corrective
21 Sept 20262201000022167Corrective
20 Sept 20262201000023715Corrective
11 Sept 20262201000028460Corrective
02 Sept 20261201000014482Corrective
03 Aug 20267201000010583Corrective
15 Jul 20262201000025691Corrective
25 Jun 202612201000034485Corrective
18 Jun 20266201000017478Corrective
11 Jun 20261201000023717Corrective
08 May 20261204000032966Preventive
13 Mar 20269201000015104Corrective
18 Feb 20262201000003328Corrective
12 Feb 20262201000032040Corrective