O-RING,VITON,151MM ID,2.5MM CS
Material 4100019425 · O-RING · Plant 1000
ASafety-criticalReorderCriticalStockout
- Material
- 4100019425
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (18 of 23 FuncLocs A/B, 5 safety/shutdown valve)
- Supplier
- ANUGRAH INSTRUMEN SENTOSA PT
- Lead time
- 44 d · P80 60 d
- Unit price
- Rp 86,067
Recommendation
- 1.Safety-critical element: installed on 5 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 77 EA/year: 77 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
- 3.Lead time ~44 days; expected demand during lead time 9.3.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 31, order up to 109.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 109 now.
- 6.Installed on 23 FuncLoc(s), 18 of them criticality A/B.
- 7.ML early warning: 99% probability of demand in the next 90 days.
Proposed purchase requisition
109 EA
Rp 9.4M · order by 01 Oct 2026
Expected arrival ≈ 44 days
Safety-critical (SCE)ML early warningLast turnaround used 54Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
57 / 97
static parameters in BoM
Rec. Min (reorder point)
31
safety stock 22
Rec. Max
109
order qty 78
Service level
99.9%
stockout risk now 93%
Unit price
Rp 86,067
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 7 issue days in the last 180 days, last issue 44 days ago, 7 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 7 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (78 units) excluded from the baseline.
Demand pattern Erratic · 36 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 6.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 23 functional locations
18 with criticality A/B · 23 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KC-226 HYDROGEN AIR COMPRESSOR | A | 1 | 6 | 2.28 |
| PX_KC-713B SPENT CAUSTIC FAN | A | 1 | 6 | 3.14 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_PP-1735 SPENT CAUSTIC PUMP | A | 1 | 4 | 1.47 |
| PX_KC-671D FEED BLOWER | A | 1 | 3 | 1.00 |
| PX_KT-460B TURBINE FOR KC-460B | A | 1 | 2 | 1.96 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_SDV-709 VD-840 SHUTDOWN VALVE | A | 1 | 2 | 0.91 |
| PX_KC-663A CONDENSATE FAN | A | 1 | 1 | 0.57 |
| PX_KC-527 METHANOL BLOWER | A | 1 | 0 | 0.57 |
| PX_PP-640A SPENT CAUSTIC PUMP | A | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 44 ± 21 days (PO history, 16 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 18 Aug 2026 | PR03 Regular replenishment | 99 | Rp 90,081 | 13 Sept 2026 | 26 d |
| 01 Jul 2026 | PR03 Regular replenishment | 73 | Rp 86,692 | 25 Aug 2026 | 55 d |
| 25 Jun 2026 | PR03 Regular replenishment | 54 | Rp 86,375 | 17 Sept 2026 | 84 d |
| 06 Jun 2026 | PR03 Regular replenishment | 51 | Rp 89,143 | 04 Aug 2026 | 59 d |
| 11 May 2026 | PR03 Regular replenishment | 77 | Rp 88,510 | 12 Jun 2026 | 32 d |
| 02 May 2026 | PR06 Regular replenishment | 86 | Rp 86,033 | 11 Jun 2026 | 40 d |
| 06 Apr 2026 | PR05 Project / turnaround | 99 | Rp 85,617 | 28 Jun 2026 | 83 d |
| 18 Mar 2026 | PR03 Regular replenishment | 77 | Rp 84,565 | 07 May 2026 | 50 d |
| 03 Mar 2026 | PR03 Regular replenishment | 33 | Rp 84,354 | 24 Mar 2026 | 21 d |
| 08 Dec 2025 | PR06 Regular replenishment | 45 | Rp 83,053 | 06 Feb 2026 | 60 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_PP-715A | Leak from packing |
| 03 Sept 2026 | Low | PX_KC-226 | KC-226 bearing temp high |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 21 Aug 2026 | Low | PX_KC-226 | KC-226 high vibration |
| 03 Aug 2026 | Medium | PX_KC-671D | KC-671D bearing temp high |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 17 Jun 2026 | Low | PX_KC-713B | Leak from packing |
| 12 Jun 2026 | High | PX_KC-713B | Inspect coupling KC-713B |
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 18 Aug 2026 | 1 | 201000006432 | Corrective |
| 12 Jul 2026 | 2 | 209000016630 | Other maintenance |
| 06 Jul 2026 | 1 | 201000013211 | Corrective |
| 20 Jun 2026 | 6 | 209000014083 | Other maintenance |
| 13 Jun 2026 | 4 | 201000023717 | Corrective |
| 30 May 2026 | 4 | 201000020779 | Corrective |
| 22 Apr 2026 | 2 | 201000020310 | Corrective |
| 03 Apr 2026 | 3 | 201000017471 | Corrective |
| 02 Apr 2026 | 1 | 201000005312 | Corrective |
| 04 Mar 2026 | 1 | 201000010251 | Corrective |
| 22 Feb 2026 | 2 | 201000005996 | Corrective |
| 04 Feb 2026 | 4 | 201000004512 | Corrective |
| 04 Feb 2026 | 7 | 201000018202 | Corrective |
| 30 Jan 2026 | 28 | 203000033471 | Turnaround |
| 29 Jan 2026 | 4 | 201000013677 | Corrective |