Sparely
DU

O-RING,NBR,224MM ID,2.5MM CS

Material 4100019439 · O-RING · Plant 1000

ASafety-criticalMonitorHealthy
Material
4100019439
Category
O-RING
Base unit
EA
MRP type
Non Stock
Criticality
A (10 of 19 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
42 d · P80 57 d
Unit price
Rp 29,759

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 39 EA/year: 38 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 3.Lead time ~42 days; expected demand during lead time 4.3.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 19, order up to 59.
  • 5.Installed on 19 FuncLoc(s), 10 of them criticality A/B.
  • 6.ML early warning: 94% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 12Single sourceAbnormal consumptionOpen PO
On hand / on order
15 / 14
next delivery 03 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
19
safety stock 15
Rec. Max
59
order qty 40
Service level
99.9%
stockout risk now 0%
Unit price
Rp 29,759
PO history
ML early warning: 94% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 21 days ago, 15 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (12 units) excluded from the baseline.

Demand pattern Erratic · 18 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 19 functional locations

10 with criticality A/B · 20 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-713B
SPENT CAUSTIC FAN
A163.14
PX_KC-867D
CONDENSATE FAN
A162.71
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KC-435A
FUEL OIL AIR COMPRESSOR
A121.00
PX_PP-807B
INHIBITOR PUMP
A121.05
PX_KT-308B
TURBINE FOR KC-308B
A201.10
PX_PP-1865A
METHANOL PUMP
A100.19
PX_PP-1399
LUBE OIL PUMP
B141.47
PX_PP-367C
METHANE PUMP
B141.90
PX_KC-582B
CAUSTIC BLOWER
S1103.57
PX_KC-458D
SLOP OIL FAN
S193.14

Lead time and procurement

Lead time 42 ± 20 days (PO history, 12 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
02 Sept 2026PR05
Project / turnaround
14Rp 29,87103 Dec 2026
open
92 d
30 Aug 2026PR06
Regular replenishment
26Rp 30,27222 Sept 202623 d
13 Aug 2026PR06
Regular replenishment
33Rp 30,24015 Sept 202633 d
31 Jul 2026PR06
Regular replenishment
16Rp 30,73426 Aug 202626 d
07 Apr 2026PR03
Regular replenishment
29Rp 28,75712 May 202635 d
28 Mar 2026PR10
Other
29Rp 30,60310 Jun 202674 d
23 Feb 2026PR03
Regular replenishment
21Rp 29,64623 Apr 202659 d
15 Feb 2026PR06
Regular replenishment
16Rp 28,87114 Mar 202627 d
15 Jan 2026PR06
Regular replenishment
18Rp 29,51024 Feb 202640 d
09 Oct 2025PR06
Regular replenishment
17Rp 30,32726 Nov 202548 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Mar 2027PX_PP-807BPump overhaul0.72
02 Jun 2027PX_PP-1007APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026MediumPX_PP-1938A[MSI-B-26-ALF-384] Permanent repair
27 Sept 2026MediumPX_PP-807BReplace bearing PP-807B
26 Sept 2026LowPX_PP-1938AOverhaul PP-1938A
19 Sept 2026MediumPX_KC-458DKC-458D lube oil filter DP high
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
17 Sept 2026MediumPX_KC-867DLeak from packing
16 Sept 2026LowPX_KC-458DKC-458D lube oil filter DP high
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
10 Sept 20261201000035065Corrective
27 Jul 20268201000000351Corrective
02 Jun 20261201000012166Corrective
22 Apr 202610201000007143Corrective
20 Apr 20265204000022204Preventive
08 Apr 20261201000035410Corrective
15 Mar 20261204000017829Preventive
11 Feb 20264201000032040Corrective
08 Jan 20261201000009440Corrective
03 Jan 202610201000005189Corrective
01 Jan 20263201000039334Corrective
22 Dec 20252201000018365Corrective
15 Dec 20251201000002502Corrective
11 Dec 20252201000008455Corrective
11 Dec 20254201000027320Corrective