Sparely
DU

O-RING,NBR,290MM ID,5.3MM CS

Material 4100019490 · O-RING · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100019490
Category
O-RING
Base unit
EA
MRP type
Non Stock
Criticality
A (10 of 15 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
PRIMA ELEKTRIK ABADI PT
Lead time
21 d · P80 21 d
Unit price
Rp 25,631

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 52 EA/year: 52 unplanned (recency-weighted compound poisson (own history)).
  • 3.Lead time ~21 days; expected demand during lead time 3.0.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 19, order up to 71.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 71 now.
  • 6.Installed on 15 FuncLoc(s), 10 of them criticality A/B.
  • 7.ML early warning: 90% probability of demand in the next 90 days.
Proposed purchase requisition
71 EA
Rp 1.8M · order by 01 Oct 2026
Expected arrival ≈ 21 days
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 22Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
19
safety stock 16
Rec. Max
71
order qty 52
Service level
100.0%
stockout risk now 56%
Unit price
Rp 25,631
PO history
ML early warning: 90% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 10 days ago, 15 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (28 units) excluded from the baseline.

Demand pattern Erratic · 22 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 15 functional locations

10 with criticality A/B · 24 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A362.81
PX_KC-752A
CONDENSATE BLOWER
A441.85
PX_PP-1769A
LUBE OIL PUMP
A130.19
PX_KC-137A
C4 PRODUCT COMPRESSOR
A121.43
PX_PP-1049
PROPYLENE PUMP
A300.19
PX_SDV-259
PP-273A SHUTDOWN VALVE
A100.06
PX_PP-467A
BFW PUMP
B371.90
PX_PP-1399
LUBE OIL PUMP
B141.47
PX_PP-1543
DILUTION STEAM PUMP
B120.62
PX_SDV-668
LUBE OIL ISOLATION
B100.06
PX_KC-773A
REFLUX COMPRESSOR
S1259.99
PX_KT-383A
TURBINE FOR KC-383A
S173.67

Lead time and procurement

Lead time 21 ± 8 days (PO history, 6 PO lines) · on-time 30%

PR dateTypeQtyUnit priceDeliveryLead time
03 Sept 2026PR06
Regular replenishment
48Rp 26,29620 Sept 202617 d
30 Jul 2026PR03
Regular replenishment
47Rp 26,18420 Aug 202621 d
19 Jun 2026PR06
Regular replenishment
23Rp 24,59310 Jul 202621 d
28 Mar 2026PR03
Regular replenishment
16Rp 25,39516 Apr 202619 d
23 Nov 2025PR06
Regular replenishment
29Rp 24,82403 Dec 202510 d
13 Nov 2025PR06
Regular replenishment
48Rp 25,86630 Nov 202517 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026EmergencyPX_KC-773AInspect coupling KC-773A
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
15 Sept 2026LowPX_KC-773AInstall scaffolding at KC-773A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
30 Aug 2026MediumPX_PP-1399Install scaffolding at PP-1399
23 Aug 2026LowPX_KC-773AKC-773A bearing temp high
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
16 Aug 2026MediumPX_PP-467AInstall scaffolding at PP-467A

Recent goods issues

Posting dateQtyOrderOrder type
21 Sept 20264201000019618Corrective
31 Aug 20266203000017844Turnaround
28 Aug 20263201000007716Corrective
10 Aug 20263201000004838Corrective
02 May 20261201000024330Corrective
10 Apr 20261201000014233Corrective
12 Mar 20263201000025388Corrective
25 Feb 20262201000000733Corrective
28 Jan 20262201000018982Corrective
23 Jan 20261201000031722Corrective
20 Jan 20263201000011893Corrective
15 Jan 20266201000032078Corrective
21 Dec 20256201000027544Corrective
15 Dec 20253201000008102Corrective
13 Dec 20252201000012757Corrective