O-RING,NBR,290MM ID,5.3MM CS
Material 4100019490 · O-RING · Plant 1000
ASafety-criticalReorderCriticalStockout
- Material
- 4100019490
- Category
- O-RING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (10 of 15 FuncLocs A/B, 3 safety/shutdown valve)
- Supplier
- PRIMA ELEKTRIK ABADI PT
- Lead time
- 21 d · P80 21 d
- Unit price
- Rp 25,631
Recommendation
- 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 52 EA/year: 52 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~21 days; expected demand during lead time 3.0.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 19, order up to 71.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 71 now.
- 6.Installed on 15 FuncLoc(s), 10 of them criticality A/B.
- 7.ML early warning: 90% probability of demand in the next 90 days.
Proposed purchase requisition
71 EA
Rp 1.8M · order by 01 Oct 2026
Expected arrival ≈ 21 days
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 22Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
19
safety stock 16
Rec. Max
71
order qty 52
Service level
100.0%
stockout risk now 56%
Unit price
Rp 25,631
PO history
ML early warning: 90% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 10 days ago, 15 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (28 units) excluded from the baseline.
Demand pattern Erratic · 22 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 15 functional locations
10 with criticality A/B · 24 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-419A TURBINE FOR KC-419A | A | 3 | 6 | 2.81 |
| PX_KC-752A CONDENSATE BLOWER | A | 4 | 4 | 1.85 |
| PX_PP-1769A LUBE OIL PUMP | A | 1 | 3 | 0.19 |
| PX_KC-137A C4 PRODUCT COMPRESSOR | A | 1 | 2 | 1.43 |
| PX_PP-1049 PROPYLENE PUMP | A | 3 | 0 | 0.19 |
| PX_SDV-259 PP-273A SHUTDOWN VALVE | A | 1 | 0 | 0.06 |
| PX_PP-467A BFW PUMP | B | 3 | 7 | 1.90 |
| PX_PP-1399 LUBE OIL PUMP | B | 1 | 4 | 1.47 |
| PX_PP-1543 DILUTION STEAM PUMP | B | 1 | 2 | 0.62 |
| PX_SDV-668 LUBE OIL ISOLATION | B | 1 | 0 | 0.06 |
| PX_KC-773A REFLUX COMPRESSOR | S | 1 | 25 | 9.99 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
Lead time and procurement
Lead time 21 ± 8 days (PO history, 6 PO lines) · on-time 30%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 03 Sept 2026 | PR06 Regular replenishment | 48 | Rp 26,296 | 20 Sept 2026 | 17 d |
| 30 Jul 2026 | PR03 Regular replenishment | 47 | Rp 26,184 | 20 Aug 2026 | 21 d |
| 19 Jun 2026 | PR06 Regular replenishment | 23 | Rp 24,593 | 10 Jul 2026 | 21 d |
| 28 Mar 2026 | PR03 Regular replenishment | 16 | Rp 25,395 | 16 Apr 2026 | 19 d |
| 23 Nov 2025 | PR06 Regular replenishment | 29 | Rp 24,824 | 03 Dec 2025 | 10 d |
| 13 Nov 2025 | PR06 Regular replenishment | 48 | Rp 25,866 | 30 Nov 2025 | 17 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 15 Sept 2026 | Low | PX_KC-773A | Install scaffolding at KC-773A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 30 Aug 2026 | Medium | PX_PP-1399 | Install scaffolding at PP-1399 |
| 23 Aug 2026 | Low | PX_KC-773A | KC-773A bearing temp high |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 16 Aug 2026 | Medium | PX_PP-467A | Install scaffolding at PP-467A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Sept 2026 | 4 | 201000019618 | Corrective |
| 31 Aug 2026 | 6 | 203000017844 | Turnaround |
| 28 Aug 2026 | 3 | 201000007716 | Corrective |
| 10 Aug 2026 | 3 | 201000004838 | Corrective |
| 02 May 2026 | 1 | 201000024330 | Corrective |
| 10 Apr 2026 | 1 | 201000014233 | Corrective |
| 12 Mar 2026 | 3 | 201000025388 | Corrective |
| 25 Feb 2026 | 2 | 201000000733 | Corrective |
| 28 Jan 2026 | 2 | 201000018982 | Corrective |
| 23 Jan 2026 | 1 | 201000031722 | Corrective |
| 20 Jan 2026 | 3 | 201000011893 | Corrective |
| 15 Jan 2026 | 6 | 201000032078 | Corrective |
| 21 Dec 2025 | 6 | 201000027544 | Corrective |
| 15 Dec 2025 | 3 | 201000008102 | Corrective |
| 13 Dec 2025 | 2 | 201000012757 | Corrective |