O-RING,EPDM,280MM ID,3.5MM CS
Material 4100019521 · O-RING · Plant 1000
ASafety-criticalLong-leadReduceExcess
- Material
- 4100019521
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (9 of 12 FuncLocs A/B, 4 safety/shutdown valve)
- Supplier
- GEMILANG SUPLINDO SENTOSA PT
- Lead time
- 62 d · P80 97 d
- Unit price
- Rp 12,485
Recommendation
- 1.Safety-critical element: installed on 4 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 39 EA/year: 39 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~62 days; expected demand during lead time 6.5.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 25, order up to 64.
- 5.Stock 758 exceeds the level to keep (64) by 694.
- 6.Long lead time: 80% of deliveries took up to 97 days and the fastest seen in its category 14 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 12 FuncLoc(s), 9 of them criticality A/B.
- 8.ML early warning: 92% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningLast turnaround used 6Single sourceAbnormal consumption
On hand / on order
758 / 0
no open PO
Today Min / Max
13 / 35
static parameters in BoM
Rec. Min (reorder point)
25
safety stock 19
Rec. Max
64
order qty 39
Service level
99.9%
stockout risk now 0%
Unit price
Rp 12,485
PO history
ML early warning: 92% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 12 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (6 units) excluded from the baseline.
Demand pattern Intermittent · 17 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 12 functional locations
9 with criticality A/B · 15 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-419A TURBINE FOR KC-419A | A | 3 | 6 | 2.81 |
| PX_KC-435A FUEL OIL AIR COMPRESSOR | A | 1 | 2 | 1.00 |
| PX_KT-460B TURBINE FOR KC-460B | A | 1 | 2 | 1.96 |
| PX_KC-250D PROPYLENE FAN | A | 1 | 0 | 0.57 |
| PX_KC-669 DEMIN WATER BLOWER | A | 1 | 0 | 0.57 |
| PX_PP-1323B CHARGE GAS PUMP | B | 2 | 2 | 1.05 |
| PX_PP-362B FUEL OIL PUMP | B | 1 | 0 | 0.19 |
| PX_SDV-641 CAUSTIC ISOLATION | B | 1 | 0 | 0.06 |
| PX_SDV-808 ON-OFF VALVE | B | 1 | 0 | 0.06 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_SDV-1392 VD-801 SHUTDOWN VALVE | S | 1 | 0 | 0.06 |
| PX_SDV-948C HE-1091 SHUTDOWN VALVE | S | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 62 ± 32 days (PO history, 11 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Jun 2026 | PR03 Regular replenishment | 21 | Rp 12,112 | 14 Aug 2026 | 62 d |
| 10 Apr 2026 | PR06 Regular replenishment | 23 | Rp 12,700 | 21 May 2026 | 41 d |
| 10 Apr 2026 | PR05 Project / turnaround | 26 | Rp 12,012 | 20 Aug 2026 | 132 d |
| 03 Mar 2026 | PR04 Regular (other) | 18 | Rp 12,973 | 03 Jun 2026 | 92 d |
| 15 Jan 2026 | PR05 Project / turnaround | 14 | Rp 12,430 | 20 May 2026 | 125 d |
| 07 Jan 2026 | PR03 Regular replenishment | 15 | Rp 12,485 | 28 Feb 2026 | 52 d |
| 17 Dec 2025 | PR03 Regular replenishment | 10 | Rp 11,894 | 15 Feb 2026 | 60 d |
| 22 Sept 2025 | PR03 Regular replenishment | 32 | Rp 12,159 | 26 Oct 2025 | 34 d |
| 11 Jul 2025 | PR03 Regular replenishment | 20 | Rp 12,687 | 16 Oct 2025 | 97 d |
| 26 Jun 2025 | PR06 Regular replenishment | 33 | Rp 12,908 | 15 Aug 2025 | 50 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 18 Apr 2026 | Medium | PX_PP-1323B | PP-1323B discharge pressure low |
| 03 Apr 2026 | Medium | PX_KT-419A | KT-419A steam leak at gland |
| 17 Mar 2026 | Medium | PX_KT-419A | Install cover plate for MCP cracking |
| 12 Dec 2025 | Low | PX_KT-460B | KT-460B governor valve hunting |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 19 Sept 2026 | 6 | 209000036917 | Other maintenance |
| 08 Aug 2026 | 1 | 201000036904 | Corrective |
| 03 Aug 2026 | 2 | 204000012685 | Preventive |
| 12 Jun 2026 | 1 | 201000023683 | Corrective |
| 31 May 2026 | 1 | 201000032912 | Corrective |
| 05 May 2026 | 10 | 201000002197 | Corrective |
| 05 Jan 2026 | 11 | 201000025317 | Corrective |
| 02 Jan 2026 | 1 | 201000008641 | Corrective |
| 28 Dec 2025 | 1 | 201000020183 | Corrective |
| 23 Nov 2025 | 5 | 201000039175 | Corrective |
| 22 Nov 2025 | 2 | 204000021668 | Preventive |
| 14 Nov 2025 | 5 | 201000000164 | Corrective |
| 14 Nov 2025 | 1 | 201000032012 | Corrective |
| 11 Nov 2025 | 6 | 203000023445 | Turnaround |
| 26 Sept 2025 | 2 | 201000005798 | Corrective |