O-RING,VITON,190MM ID,5.3MM CS
Material 4100019555 · O-RING · Plant 1000
ASafety-criticalReorderNormalBelow reorder point
- Material
- 4100019555
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (9 of 12 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 42 d · P80 49 d
- Unit price
- Rp 12,064
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 31 EA/year: 31 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~42 days; expected demand during lead time 3.5.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 21, order up to 52.
- 5.On hand 11 + on order 7 is at or below the reorder point: order 34 now.
- 6.Installed on 12 FuncLoc(s), 9 of them criticality A/B.
- 7.ML early warning: 85% probability of demand in the next 90 days.
Proposed purchase requisition
34 EA
Rp 410,176 · order by 01 Oct 2026
Expected arrival ≈ 42 days
Safety-critical (SCE)ML early warningLast turnaround used 6Single sourceOpen PO
On hand / on order
11 / 7
next delivery 05 Oct 2026
Today Min / Max
7 / 10
static parameters in BoM
Rec. Min (reorder point)
21
safety stock 18
Rec. Max
52
order qty 31
Service level
100.0%
stockout risk now 0%
Unit price
Rp 12,064
PO history
ML early warning: 85% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 34 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (6 units) excluded from the baseline.
Demand pattern Lumpy · 12 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 12 functional locations
9 with criticality A/B · 12 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-536A LUBE OIL BLOWER | A | 1 | 11 | 4.42 |
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PY_KC-636C SLOP OIL COMPRESSOR | A | 1 | 1 | 0.57 |
| PX_PP-1383 PROPYLENE PUMP | A | 1 | 0 | 0.19 |
| PX_PP-739 ETHYLENE PUMP | A | 1 | 0 | 0.19 |
| PX_SDV-958 CL-1833 SHUTDOWN VALVE | A | 1 | 0 | 0.06 |
| PX_PP-1399 LUBE OIL PUMP | B | 1 | 4 | 1.47 |
| PX_PP-724 METHANE PUMP | B | 1 | 0 | 0.19 |
| PX_SDV-398A SLOP OIL ISOLATION | S | 1 | 2 | 0.91 |
| PX_KC-486 CONDENSATE AIR COMPRESSOR | S | 1 | 0 | 0.57 |
| PX_KT-875 TURBINE FOR KC-875 | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 42 ± 29 days (PO history, 10 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 24 Jun 2026 | PR06 Regular replenishment | 26 | Rp 12,089 | 06 Jul 2026 | 12 d |
| 26 May 2026 | PR06 Regular replenishment | 7 | Rp 12,039 | 05 Oct 2026 open | 132 d |
| 01 May 2026 | PR03 Regular replenishment | 17 | Rp 11,581 | 05 Jun 2026 | 35 d |
| 31 Mar 2026 | PR03 Regular replenishment | 16 | Rp 12,628 | 25 May 2026 | 55 d |
| 22 Mar 2026 | PR06 Regular replenishment | 24 | Rp 12,481 | 27 Apr 2026 | 36 d |
| 18 Mar 2026 | PR03 Regular replenishment | 16 | Rp 11,972 | 15 Apr 2026 | 28 d |
| 09 Feb 2026 | PR03 Regular replenishment | 15 | Rp 11,829 | 17 Mar 2026 | 36 d |
| 27 Nov 2025 | PR03 Regular replenishment | 26 | Rp 12,598 | 12 Jan 2026 | 46 d |
| 24 Aug 2025 | PR03 Regular replenishment | 18 | Rp 12,296 | 21 Sept 2025 | 28 d |
| 11 Jul 2025 | PR06 Regular replenishment | 17 | Rp 11,608 | 27 Aug 2025 | 47 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | High | PX_KC-536A | Overhaul |
| 30 Aug 2026 | Medium | PX_PP-1399 | Install scaffolding at PP-1399 |
| 08 Aug 2026 | High | PX_KC-536A | KC-536A bearing temp high |
| 24 Jul 2026 | High | PX_KC-536A | Install scaffolding at KC-536A |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 05 Jul 2026 | Medium | PX_KC-536A | Leak from packing |
| 26 Jun 2026 | Medium | PX_SDV-398A | SDV-398A fail to close |
| 24 Jun 2026 | Medium | PX_KC-536A | KC-536A bearing temp high |
| 09 Jun 2026 | High | PX_PP-1399 | Replace bearing PP-1399 |
| 18 Apr 2026 | Medium | PX_PP-1399 | Repair insulation PP-1399 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 28 Aug 2026 | 5 | 201000007926 | Corrective |
| 13 Jun 2026 | 4 | 209000014321 | Other maintenance |
| 09 May 2026 | 7 | 201000024899 | Corrective |
| 08 Jan 2026 | 4 | 203000006950 | Turnaround |
| 03 Jan 2026 | 1 | 201000014604 | Corrective |
| 21 Dec 2025 | 6 | 201000016287 | Corrective |
| 20 Dec 2025 | 2 | 201000021150 | Corrective |
| 12 Dec 2025 | 9 | 201000000773 | Corrective |
| 08 Dec 2025 | 1 | 201000028486 | Corrective |
| 20 Nov 2025 | 2 | 203000038363 | Turnaround |
| 19 Nov 2025 | 1 | 204000013871 | Preventive |
| 18 Sept 2025 | 8 | 201000039916 | Corrective |
| 05 Jul 2025 | 4 | 201000030028 | Corrective |
| 30 Jun 2025 | 2 | 209000008119 | Other maintenance |