O-RING,VITON,252MM ID,5.3MM CS

Material 4100019559 · O-RING · Plant 1000

ASafety-criticalLong-leadMaintainHealthy
Material
4100019559
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (7 of 11 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
DUTA ENERGI ABADI PT
Lead time
65 d · P80 107 d
Unit price
Rp 12,930

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 46 EA/year: 45 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 3.Lead time ~65 days; expected demand during lead time 7.9.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 29, order up to 76.
  • 5.Long lead time: 80% of deliveries took up to 107 days and the fastest seen in its category 14 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 11 FuncLoc(s), 7 of them criticality A/B.
  • 7.ML early warning: 97% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningLast turnaround used 16Single sourceOpen PO
On hand / on order
59 / 34
next delivery 13 Oct 2026
Today Min / Max
16 / 43
static parameters in BoM
Rec. Min (reorder point)
29
safety stock 22
Rec. Max
76
order qty 47
Service level
99.9%
stockout risk now 0%
Unit price
Rp 12,930
PO history
ML early warning: 97% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 5 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (16 units) excluded from the baseline.

Demand pattern Lumpy · 17 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 11 functional locations

7 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1530
PROPYLENE PUMP
A141.47
PX_KC-396
WASH WATER BLOWER
A131.43
PX_SDV-889
ETHYLENE ISOLATION
A100.06
PX_PP-339A
METHANE PUMP
B162.33
PX_PP-1498C
CHARGE GAS PUMP
B151.90
PX_PP-483B
LEAN AMINE PUMP
B151.90
PX_PP-490A
REFLUX PUMP
B110.19
PX_PP-1141D
DILUTION STEAM PUMP
C100.19
PX_KC-879A
CONDENSATE FAN
S162.71
PX_PP-148A
REFLUX PUMP
S120.62
PX_SDV-336B
RICH AMINE ISOLATION
S100.06

Lead time and procurement

Lead time 65 ± 32 days (PO history, 13 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
25 Aug 2026PR06
Regular replenishment
16Rp 13,12728 Oct 2026
open
64 d
07 Aug 2026PR03
Regular replenishment
18Rp 13,57413 Oct 2026
open
67 d
25 Jul 2026PR03
Regular replenishment
29Rp 12,77305 Sept 202642 d
26 Jun 2026PR03
Regular replenishment
25Rp 12,81404 Aug 202639 d
04 Apr 2026PR03
Regular replenishment
24Rp 13,24622 Jul 2026109 d
29 Mar 2026PR04
Regular (other)
35Rp 12,72010 Jul 2026103 d
18 Mar 2026PR03
Regular replenishment
13Rp 12,86429 Apr 202642 d
05 Feb 2026PR03
Regular replenishment
31Rp 13,22528 Mar 202651 d
03 Jan 2026PR03
Regular replenishment
19Rp 12,85218 Feb 202646 d
18 Dec 2025PR03
Regular replenishment
30Rp 12,92306 Feb 202650 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Mar 2027PX_PP-339APump overhaul0.72
02 Jul 2027PX_PP-1498CPump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
24 Sept 2026LowPX_KC-879AInspect coupling KC-879A
07 Sept 2026MediumPX_KC-879AReplace lamp as per PM finding
25 Aug 2026LowPX_PP-1498C[MSI-B-26-LAH-309/M] Replace line
19 Aug 2026MediumPX_PP-483BPP-483B abnormal noise
22 Jul 2026HighPX_PP-1498CInstall scaffolding at PP-1498C
19 Jul 2026LowPX_PP-339APP-339A seal leak
12 Jul 2026MediumPX_PP-1530Replace bearing PP-1530
29 Jun 2026MediumPX_PP-483BOil leak at PP-483B bearing housing
16 Jun 2026MediumPX_PP-1498COverhaul PP-1498C

Recent goods issues

Posting dateQtyOrderOrder type
26 Sept 20262201000025207Corrective
03 Sept 20261201000031484Corrective
12 Aug 20261201000022527Corrective
09 Jul 20265201000023095Corrective
07 Jun 20262201000004959Corrective
25 Apr 20261204000012220Preventive
23 Apr 20264201000024864Corrective
16 Apr 20262201000026573Corrective
20 Mar 20262201000009227Corrective
17 Feb 20265201000002211Corrective
22 Dec 20256201000006328Corrective
19 Dec 202510203000033370Turnaround
18 Dec 20254203000014056Turnaround
13 Dec 20255201000000570Corrective
02 Dec 20254201000039183Corrective