Sparely
DU

O-RING,VITON,231MM ID,2.5MM CS

Material 4100019564 · O-RING · Plant 1000

ASafety-criticalReduceExcess
Material
4100019564
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 7 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
21 d · P80 20 d
Unit price
Rp 52,363

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 19 EA/year: 18 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
  • 3.Lead time ~21 days; expected demand during lead time 1.0.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 31.
  • 5.Stock 361 exceeds the level to keep (31) by 330.
  • 6.Installed on 7 FuncLoc(s), 3 of them criticality A/B.
  • 7.ML early warning: 50% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningSingle source
On hand / on order
361 / 0
no open PO
Today Min / Max
3 / 9
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 11
Rec. Max
31
order qty 19
Service level
100.0%
stockout risk now 0%
Unit price
Rp 52,363
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 100 days ago, 3 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (10 units) excluded from the baseline.

Demand pattern Intermittent · 8 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 7 functional locations

3 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-316D
METHANOL FAN
A151.43
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KC-371B
BOTTOM FAN
B100.57
PX_KC-582B
CAUSTIC BLOWER
S1103.57
PX_KT-202
TURBINE FOR KC-202
S142.81
PX_KT-264A
TURBINE FOR KC-264A
S142.39
PX_SDV-949
VD-1618 SHUTDOWN VALVE
S100.06

Lead time and procurement

Lead time 21 ± 12 days (PO history, 4 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
16 Sept 2026PR03
Regular replenishment
12Rp 52,43724 Sept 20268 d
11 Nov 2025PR03
Regular replenishment
16Rp 52,28824 Nov 202513 d
31 Aug 2025PR05
Project / turnaround
8Rp 54,05415 Sept 202515 d
19 Jun 2025PR06
Regular replenishment
21Rp 50,15516 Jul 202527 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
01 Sept 2026HighPX_KC-582BKC-582B high vibration
26 Aug 2026LowPX_KC-582BPainting KC-582B
10 Aug 2026MediumPX_KC-316DOverhaul
03 Aug 2026MediumPX_KC-316DPainting KC-316D
08 Jul 2026LowPX_KC-582BInstall scaffolding at KC-582B
11 Jun 2026LowPX_KT-264ALeak from packing
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026MediumPX_KC-316DKC-316D high vibration

Recent goods issues

Posting dateQtyOrderOrder type
23 Jun 20264201000018159Corrective
27 Jan 20261201000018107Corrective
23 Jan 20261201000006146Corrective
19 Dec 20251201000036958Corrective
02 Dec 202510201000002935Corrective
30 Oct 20254201000007876Corrective
26 Aug 202510203000006603Turnaround
09 Aug 20257201000034091Corrective
12 Jul 20252201000028105Corrective