O-RING,NBR,262MM ID,3.5MM CS

Material 4100019592 · O-RING · Plant 1000

AReorderCriticalStockout
Material
4100019592
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 9 FuncLocs A/B)
Supplier
MEGA ELEKTRIK ABADI PT
Lead time
45 d · P80 73 d
Unit price
Rp 15,092

Recommendation

  • 1.Forecast 13 EA/year: 13 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~45 days; expected demand during lead time 1.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 23.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 23 now.
  • 5.Installed on 9 FuncLoc(s), 5 of them criticality A/B.
  • 6.ML early warning: 84% probability of demand in the next 90 days.
Proposed purchase requisition
23 EA
Rp 347,105 · order by 01 Oct 2026
Expected arrival ≈ 45 days
ML early warningSingle sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
4 / 11
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 9
Rec. Max
23
order qty 13
Service level
100.0%
stockout risk now 58%
Unit price
Rp 15,092
PO history
ML early warning: 84% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 98 days ago, 11 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Lumpy · 11 issue days · 4 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 9 functional locations

5 with criticality A/B · 14 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-397A
TURBINE FOR KC-397A
A252.81
PX_PP-326A
INHIBITOR PUMP
A131.47
PX_KC-397A
DILUTION STEAM FAN
A110.57
PX_KC-669
DEMIN WATER BLOWER
A200.57
PX_PP-473A
CONDENSATE PUMP
B161.47
PX_KC-773A
REFLUX COMPRESSOR
S1259.99
PX_KT-624A
TURBINE FOR KC-624A
S132.39
PX_KT-778A
TURBINE FOR KC-778A
S101.10
PX_KT-875
TURBINE FOR KC-875
S401.10

Lead time and procurement

Lead time 45 ± 19 days (PO history, 4 PO lines) · on-time 58%

PR dateTypeQtyUnit priceDeliveryLead time
10 Aug 2026PR03
Regular replenishment
9Rp 14,99430 Sept 202651 d
11 Oct 2025PR06
Regular replenishment
11Rp 15,18924 Dec 202574 d
25 Aug 2025PR03
Regular replenishment
7Rp 14,76527 Sept 202533 d
28 May 2025PR03
Regular replenishment
10Rp 15,39309 Aug 202573 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026EmergencyPX_KC-773AInspect coupling KC-773A
15 Sept 2026LowPX_KC-773AInstall scaffolding at KC-773A
12 Sept 2026MediumPX_PP-473APainting PP-473A
23 Aug 2026LowPX_KC-773AKC-773A bearing temp high
10 Aug 2026LowPX_KC-773AKC-773A high vibration
09 Aug 2026MediumPX_KC-773AInspect coupling KC-773A
03 Aug 2026MediumPX_KC-773ALeak from packing
20 Jul 2026MediumPX_KC-773AKC-773A high vibration
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
13 Jul 2026LowPX_KC-773AKC-773A lube oil filter DP high

Recent goods issues

Posting dateQtyOrderOrder type
25 Jun 202611201000034485Corrective
17 May 202614209000009186Other maintenance
11 Mar 20269201000025906Corrective
16 Jan 20261201000026554Corrective
11 Jan 20261204000006058Preventive
27 Dec 20251201000019463Corrective
20 Nov 20251201000029125Corrective
17 Nov 20251201000028386Corrective
14 Sept 20252209000027092Other maintenance
02 Sept 20251201000037801Corrective
14 Jun 20256201000015271Corrective