O-RING,VITON,125MM ID,3.5MM CS

Material 4100019593 · O-RING · Plant 1000

ASafety-criticalLong-leadMonitorHealthy
Material
4100019593
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 7 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
BERKAH LOGAM GLOBAL PT
Lead time
63 d · P80 128 d
Unit price
Rp 14,161

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 16 EA/year: 16 unplanned (recency-weighted compound poisson (own history)).
  • 3.Lead time ~63 days; expected demand during lead time 2.7.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 13, order up to 30.
  • 5.Long lead time: 80% of deliveries took up to 128 days and the fastest seen in its category 14 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 7 FuncLoc(s), 5 of them criticality A/B.
  • 7.ML early warning: 86% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningLast turnaround used 4Single sourceOpen PO
On hand / on order
7 / 12
next delivery 02 Jan 2027
Today Min / Max
7 / 10
static parameters in BoM
Rec. Min (reorder point)
13
safety stock 11
Rec. Max
30
order qty 17
Service level
99.9%
stockout risk now 0%
Unit price
Rp 14,161
PO history
ML early warning: 86% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 20 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (4 units) excluded from the baseline.

Demand pattern Lumpy · 10 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 7 functional locations

5 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-854C
FEED FAN
A172.28
PX_SDV-676
CAUSTIC ISOLATION
A141.34
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_PP-1370C
FUEL OIL PUMP
B100.19
PX_PP-413C
LEAN AMINE PUMP
B100.19
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_SDV-1278
ON-OFF VALVE
S100.06

Lead time and procurement

Lead time 63 ± 43 days (PO history, 7 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
19 Sept 2026PR05
Project / turnaround
4Rp 13,79202 Feb 2027
open
136 d
02 Aug 2026PR06
Regular replenishment
6Rp 14,55427 Aug 202625 d
27 Jul 2026PR01
Import / long-lead
8Rp 14,38102 Jan 2027
open
159 d
03 Jul 2026PR03
Regular replenishment
6Rp 14,45021 Aug 202649 d
10 Dec 2025PR06
Regular replenishment
12Rp 13,93509 Jan 202630 d
16 Nov 2025PR03
Regular replenishment
12Rp 14,16120 Feb 202696 d
21 Aug 2025PR03
Regular replenishment
5Rp 13,85506 Oct 202546 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Sept 2026MediumPX_KC-854COverhaul
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
29 Jul 2026MediumPX_KC-854CInstall scaffolding at KC-854C
17 Jul 2026LowPX_KC-854CPainting KC-854C
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
13 May 2026LowPX_KT-447KT-447 trip test
01 May 2026MediumPX_SDV-676Check SDV-676.ok
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447

Recent goods issues

Posting dateQtyOrderOrder type
11 Sept 20261201000028460Corrective
13 Jul 20262201000029732Corrective
23 Mar 20261201000013730Corrective
30 Jan 20262201000025135Corrective
20 Dec 20254201000036353Corrective
30 Nov 20254203000012255Turnaround
12 Nov 20252201000001935Corrective
07 Sept 20255201000025638Corrective
01 Sept 20251201000002141Corrective
01 Aug 20257201000026175Corrective
26 May 20251201000004495Corrective