O-RING,VITON,125MM ID,3.5MM CS
Material 4100019593 · O-RING · Plant 1000
ASafety-criticalLong-leadMonitorHealthy
- Material
- 4100019593
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 7 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- BERKAH LOGAM GLOBAL PT
- Lead time
- 63 d · P80 128 d
- Unit price
- Rp 14,161
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 16 EA/year: 16 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~63 days; expected demand during lead time 2.7.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 13, order up to 30.
- 5.Long lead time: 80% of deliveries took up to 128 days and the fastest seen in its category 14 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 7 FuncLoc(s), 5 of them criticality A/B.
- 7.ML early warning: 86% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningLast turnaround used 4Single sourceOpen PO
On hand / on order
7 / 12
next delivery 02 Jan 2027
Today Min / Max
7 / 10
static parameters in BoM
Rec. Min (reorder point)
13
safety stock 11
Rec. Max
30
order qty 17
Service level
99.9%
stockout risk now 0%
Unit price
Rp 14,161
PO history
ML early warning: 86% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 20 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (4 units) excluded from the baseline.
Demand pattern Lumpy · 10 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 7 functional locations
5 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-854C FEED FAN | A | 1 | 7 | 2.28 |
| PX_SDV-676 CAUSTIC ISOLATION | A | 1 | 4 | 1.34 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_PP-1370C FUEL OIL PUMP | B | 1 | 0 | 0.19 |
| PX_PP-413C LEAN AMINE PUMP | B | 1 | 0 | 0.19 |
| PX_KT-447 TURBINE FOR KC-447 | S | 1 | 13 | 6.24 |
| PX_SDV-1278 ON-OFF VALVE | S | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 63 ± 43 days (PO history, 7 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 19 Sept 2026 | PR05 Project / turnaround | 4 | Rp 13,792 | 02 Feb 2027 open | 136 d |
| 02 Aug 2026 | PR06 Regular replenishment | 6 | Rp 14,554 | 27 Aug 2026 | 25 d |
| 27 Jul 2026 | PR01 Import / long-lead | 8 | Rp 14,381 | 02 Jan 2027 open | 159 d |
| 03 Jul 2026 | PR03 Regular replenishment | 6 | Rp 14,450 | 21 Aug 2026 | 49 d |
| 10 Dec 2025 | PR06 Regular replenishment | 12 | Rp 13,935 | 09 Jan 2026 | 30 d |
| 16 Nov 2025 | PR03 Regular replenishment | 12 | Rp 14,161 | 20 Feb 2026 | 96 d |
| 21 Aug 2025 | PR03 Regular replenishment | 5 | Rp 13,855 | 06 Oct 2025 | 46 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | Medium | PX_KC-854C | Overhaul |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 29 Jul 2026 | Medium | PX_KC-854C | Install scaffolding at KC-854C |
| 17 Jul 2026 | Low | PX_KC-854C | Painting KC-854C |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 13 May 2026 | Low | PX_KT-447 | KT-447 trip test |
| 01 May 2026 | Medium | PX_SDV-676 | Check SDV-676.ok |
| 19 Apr 2026 | Low | PX_KT-447 | Follow up after steam upset KT-447 |
| 30 Mar 2026 | Low | PX_KT-447 | Leak from packing |
| 28 Mar 2026 | Medium | PX_KT-447 | Follow up after steam upset KT-447 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 11 Sept 2026 | 1 | 201000028460 | Corrective |
| 13 Jul 2026 | 2 | 201000029732 | Corrective |
| 23 Mar 2026 | 1 | 201000013730 | Corrective |
| 30 Jan 2026 | 2 | 201000025135 | Corrective |
| 20 Dec 2025 | 4 | 201000036353 | Corrective |
| 30 Nov 2025 | 4 | 203000012255 | Turnaround |
| 12 Nov 2025 | 2 | 201000001935 | Corrective |
| 07 Sept 2025 | 5 | 201000025638 | Corrective |
| 01 Sept 2025 | 1 | 201000002141 | Corrective |
| 01 Aug 2025 | 7 | 201000026175 | Corrective |
| 26 May 2025 | 1 | 201000004495 | Corrective |