O-RING,EPDM,83MM ID,5.3MM CS
Material 4100019606 · O-RING · Plant 1000
ASafety-criticalMonitorSlow-moving
- Material
- 4100019606
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 8 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 28 d · P80 31 d
- Unit price
- Rp 245,040
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 7.0 EA/year: 7.0 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~28 days; expected demand during lead time 0.5.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 14.
- 5.Installed on 8 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 71% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 8Single sourceAbnormal consumptionOpen PO
On hand / on order
11 / 11
next delivery 07 Oct 2026
Today Min / Max
6 / 13
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
14
order qty 8
Service level
100.0%
stockout risk now 0%
Unit price
Rp 245,040
PO history
ML early warning: 71% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 226 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (8 units) excluded from the baseline.
Demand pattern Lumpy · 8 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 8 functional locations
4 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_PP-1991A FEED PUMP | A | 1 | 2 | 0.62 |
| PX_KC-397A DILUTION STEAM FAN | A | 1 | 1 | 0.57 |
| PX_PP-306A BFW PUMP | B | 2 | 1 | 0.19 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
| PX_KC-511C FUEL OIL FAN | S | 1 | 1 | 0.57 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
| PX_SDV-468 DEMIN WATER ISOLATION | S | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 28 ± 12 days (PO history, 9 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Sept 2026 | PR06 Regular replenishment | 11 | Rp 243,737 | 07 Oct 2026 open | 24 d |
| 24 Jul 2026 | PR06 Regular replenishment | 8 | Rp 248,632 | 13 Aug 2026 | 20 d |
| 16 May 2026 | PR06 Regular replenishment | 10 | Rp 241,377 | 14 Jun 2026 | 29 d |
| 20 Oct 2025 | PR06 Regular replenishment | 6 | Rp 244,814 | 05 Nov 2025 | 16 d |
| 18 Oct 2025 | PR03 Regular replenishment | 12 | Rp 251,165 | 20 Nov 2025 | 33 d |
| 28 Aug 2025 | PR04 Regular (other) | 14 | Rp 250,620 | 17 Oct 2025 | 50 d |
| 14 Jun 2025 | PR03 Regular replenishment | 6 | Rp 239,240 | 10 Jul 2025 | 26 d |
| 18 May 2025 | PR03 Regular replenishment | 13 | Rp 247,013 | 17 Jun 2025 | 30 d |
| 10 May 2025 | PR06 Regular replenishment | 5 | Rp 245,040 | 03 Jun 2025 | 24 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 07 Feb 2026 | Medium | PX_KT-624A | Replace lamp as per PM finding |
| 04 Jan 2026 | Medium | PX_KT-513 | KT-513 governor valve hunting |
| 30 Sept 2025 | Low | PX_PP-1991A | Replace lamp as per PM finding |
| 24 Jul 2025 | Medium | PX_KC-511C | Install scaffolding at KC-511C |
| 02 Jul 2025 | Low | PX_KC-397A | Painting KC-397A |
| 17 Jun 2025 | Medium | PX_KT-624A | [MSI-B-25-SWV-127/M] Replace line |
| 10 May 2025 | Medium | PX_PP-306A | Replace lamp as per PM finding |
| 03 May 2025 | Medium | PX_KT-513 | KT-513 governor valve hunting |
| 03 May 2025 | Low | PX_PP-1991A | Replace bearing PP-1991A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 17 Feb 2026 | 6 | 201000029237 | Corrective |
| 07 Feb 2026 | 1 | 201000000444 | Corrective |
| 08 Jan 2026 | 6 | 201000014005 | Corrective |
| 29 Dec 2025 | 1 | 201000027002 | Corrective |
| 27 Dec 2025 | 2 | 203000006078 | Turnaround |
| 07 Dec 2025 | 3 | 201000037867 | Corrective |
| 13 Nov 2025 | 1 | 201000032012 | Corrective |
| 07 Nov 2025 | 6 | 203000029164 | Turnaround |
| 12 Oct 2025 | 1 | 201000036265 | Corrective |
| 02 Sept 2025 | 1 | 201000018068 | Corrective |