O-RING,NBR,257MM ID,2.5MM CS
Material 4100019618 · O-RING · Plant 1000
ASafety-criticalReorderNormalBelow reorder point
- Material
- 4100019618
- Category
- O-RING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (5 of 8 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- RAJAWALI TEKNIK PRATAMA PT
- Lead time
- 21 d · P80 19 d
- Unit price
- Rp 194,759
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 14 EA/year: 14 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~21 days; expected demand during lead time 0.8.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 26.
- 5.On hand 2 + on order 0 is at or below the reorder point: order 24 now.
- 6.Installed on 8 FuncLoc(s), 5 of them criticality A/B.
- 7.ML early warning: 35% probability of demand in the next 90 days.
Proposed purchase requisition
24 EA
Rp 4.7M · order by 01 Oct 2026
Expected arrival ≈ 21 days
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 26Single source
On hand / on order
2 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 12
Rec. Max
26
order qty 14
Service level
100.0%
stockout risk now 18%
Unit price
Rp 194,759
PO history
ML early warning: 35% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 57 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (26 units) excluded from the baseline.
Demand pattern Lumpy · 6 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 8 functional locations
5 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-671D FEED BLOWER | A | 1 | 3 | 1.00 |
| PX_PP-207 INHIBITOR PUMP | A | 1 | 3 | 1.47 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PY_PP-1063 METHANE PUMP | A | 1 | 0 | 0.19 |
| PX_KC-371B BOTTOM FAN | B | 1 | 0 | 0.57 |
| PX_SDV-1594 METHANE ISOLATION | S | 3 | 3 | 0.91 |
| PX_SDV-1725 HE-1279B SHUTDOWN VALVE | S | 1 | 2 | 0.48 |
| PX_KC-373B CONDENSATE BLOWER | S | 1 | 0 | 0.57 |
Lead time and procurement
Lead time 21 ± 9 days (PO history, 5 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Jul 2026 | PR06 Regular replenishment | 13 | Rp 199,986 | 05 Aug 2026 | 14 d |
| 22 May 2026 | PR05 Project / turnaround | 15 | Rp 192,934 | 10 Jun 2026 | 19 d |
| 16 Nov 2025 | PR03 Regular replenishment | 15 | Rp 194,759 | 07 Dec 2025 | 21 d |
| 15 Nov 2025 | PR06 Regular replenishment | 22 | Rp 201,097 | 27 Nov 2025 | 12 d |
| 30 Sept 2025 | PR06 Regular replenishment | 23 | Rp 189,181 | 17 Oct 2025 | 17 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 03 Aug 2026 | Medium | PX_KC-671D | KC-671D bearing temp high |
| 07 Jun 2026 | High | PX_KC-671D | Install scaffolding at KC-671D |
| 06 Jun 2026 | Medium | PX_SDV-1594 | Leak from packing |
| 30 May 2026 | Medium | PX_SDV-1725 | SDV-1725 limit switch faulty |
| 27 May 2026 | Medium | PX_PP-207 | Leak from packing |
| 23 Nov 2025 | High | PX_SDV-1594 | SDV-1594 limit switch faulty |
| 01 Nov 2025 | Medium | PX_PP-207 | PP-207 abnormal noise |
| 16 Jun 2025 | Low | PX_KC-671D | Install scaffolding at KC-671D |
| 14 Jun 2025 | Medium | PX_PP-207 | PP-207 high vibration |
| 02 Jun 2025 | Medium | PX_SDV-1594 | Painting SDV-1594 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 05 Aug 2026 | 4 | 201000010969 | Corrective |
| 08 Mar 2026 | 1 | 201000002761 | Corrective |
| 11 Jan 2026 | 1 | 201000033090 | Corrective |
| 24 Dec 2025 | 6 | 203000006078 | Turnaround |
| 21 Dec 2025 | 2 | 203000033370 | Turnaround |
| 04 Dec 2025 | 4 | 203000037280 | Turnaround |
| 30 Nov 2025 | 6 | 203000009623 | Turnaround |
| 28 Nov 2025 | 8 | 201000005031 | Corrective |
| 11 Nov 2025 | 8 | 203000039046 | Turnaround |
| 19 Aug 2025 | 2 | 209000020318 | Other maintenance |
| 12 Jun 2025 | 8 | 201000028886 | Corrective |